Originally Posted by waves View Post
My secondary source for the cost numbers stem from Daryl's Blog post here: https://blog.daryldelacruz.com/2015/12/06/capital-costs-of-canadian-rail-transit-systems/. If he's reading this and has a newer post out I would be interested to see it

If you want to take a closer look at my calcs you can follow along in my crude spreadsheet here: https://1drv.ms/x/s!AjWWltw_HSwzh8lAGO2et-WqzET3EA

Also fredinno, Cut and Cover for 13th to 23rd for the Lonsdale Line is suggested on the profile.
Thanks.

Though, looking through the numbers, I can't help but feel that this is a low-ball estimate.

I'd be iffy on Cut-and-cover on 13-17th; it's just too dense yet to start cutting up the road. Starting the cut on 17th avoids the remaining skyscrapers

You also list Broadway to Artubus as $1.8 Billion, clearly too low, even for 2010 numbers. The actual cost is increased heavily due to real estate costs- and Lonsdale is not cheap.

I'll try to reflect this with a 25% contingency cost for both yours and my lines.

Also, the number of Stations for the Lonsdale is 9, not 8. Unless it's a spur of the Millennium?

Lastly, there's no cost estimate for At-grade- BC. I'll assume $50M/km, to make the comparison more fair.

Where is the section above-grade? I want to make this as fair as possible, so I didn't touch it.



With these numbers:

With a 25% contingency for RE costs, the Lonsdale Line is $3080M, and the Purple Line is $2498M.

I doubt either would be built all at once, considering both would have comparable costs to the Broadway Extension, which is already an unprecedented amount of money on one extension.

The Purple Line is about 20% cheaper for the entire route. Is that worth bypassing Commercial St?

I'll leave that for everyone else to decide.



In conclusion: Admittedly, the Commerical-Broadway Line, though underpriced, is not as bad as I thought. Definitely some advantages, especially in a high-growth scenario where the land around current Skytrain Lines gets built up.


PS: Made a few errors, the Lonsdale line should be $3.15 Billion; see my post below for more details.

Last edited by fredinno; Nov 9, 2018 at 11:21 PM.
Reply With Quote
     
     
End
 
 
 

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 6:21 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.