from the website - june 26
Progress on the project is now moving ahead strongly.
Most of the windows have been installed, the brickwork and concrete work is complete. The fibre cement panels that make up the rest of the facade will be installed in the coming weeks.
Most of the interior partitions have been installed and much of the plumbing rough-in finished. All of the radiant heating has been installed, and the fan coil units in each suite that provide air conditioning are in process.
The elevator is waiting in crates in the basement and the geothermal heat pumps are now on site. We expect to complete the roof by July and then, with the building dry, we’ll move quickly to completion, installing the gyprock, flooring, electrical and lastly, the cabinetry.