Forming started for 7th floor walls and posts on the west end of this 8s building. Working on the 6th floor in the middle section. Still have not poured the ground floor slab for the east end fronting Richmond. The east tower crane boom has been anchored with cables for over a week now so they may be having technical issues with it.