Ādisōke library project goes further over budget, faces more delays
New funding request would push budget to $352 million, still no word on opening date
Arthur White-Crummey · CBC News
Posted: May 22, 2026 7:06 PM EDT | Last Updated: May 22
The Ādisōke library project on LeBreton Flats is facing another budget overrun, a few more months of delays and still does not have an opening date to the public.
That update came Friday in a new report to council's finance and corporate services committee seeking an additional $18.5 million in funding for the project.
Last year, city staff announced that the contractor was reporting delays and the library would not open to the public in summer 2026 as previously expected.
At the time, the contractor was expecting to complete the project in September of this year, but staff could not give a timeline for when it would be actually open to the public.
The new report says that the contractor's schedule has "not stablized" in the months since. Instead, it has faced "additional delays."
Construction is now about 85 per cent complete. The report says the contractor's most recent schedule submission gives a date of December 2026 for completing the project, though the city still can't give a date for when it will open.
That's about 12 months behind the contractual date for it to be completed.
At the same time, the city said the new timeline will mean added costs for the project, which already had a budget of $334 million. The report says the project has already "reached the limits of its approved funding."
The extra $18.5 million is supposed to fund oversight and support services, plus top up for the contingency buffer.
The city will have to kick in most but not all of those funds, since Ādisōke is a joint project of it, the Ottawa Public Library and Library and Archives Canada.
The project has faced repeated opening delays. Late last decade the hope was 2024. Until last year, it was set for summer 2026.
It has also faced previous budget increases.
The cost was initially supposed to be fixed at $175 million, with the federal government paying $71 million. The city would then pick up the remaining $104 million, plus an additional $18 million for a 200-spot underground garage.
That increased 75 per cent to $334 million once the bids were in back in 2021.
https://www.cbc.ca/news/canada/ottawa/adisoke-library-ottawa-timeline-cost-schedule-9.7209623