  #1021  
Old Posted Dec 20, 2017, 10:04 PM
left of center's Avatar
left of center left of center is offline
1st Ward
 
Join Date: Sep 2006
Location: The Big Onion
Posts: 2,570
^ 130 N Franklin is the long shot project I'm really hoping materializes in this boom. Probably pretty unlikely though with all the new office space planned for and currently being added to the market.
     
     
  #1022  
Old Posted Dec 21, 2017, 5:09 AM
SolarWind's Avatar
SolarWind SolarWind is offline
Chicago
 
Join Date: Jun 2006
Posts: 5,477
December 20, 2017

     
     
  #1023  
Old Posted Dec 22, 2017, 12:02 AM
harryc's Avatar
harryc harryc is offline
Registered User
 
Join Date: Jun 2007
Location: Oak Park, Il
Posts: 14,989
Dec 20







__________________
Harry C - Urbanize Chicago- My Flickr stream HRC_OakPark
The man who trades freedom for security does not deserve nor will he ever receive either. B Franklin.
     
     
  #1024  
Old Posted Dec 27, 2017, 12:52 AM
kolchak's Avatar
kolchak kolchak is offline
Registered User
 
Join Date: Mar 2008
Posts: 873
December 26 -



Last edited by kolchak; Dec 27, 2017 at 11:27 PM.
     
     
  #1025  
Old Posted Dec 27, 2017, 2:46 AM
LouisVanDerWright LouisVanDerWright is offline
Registered User
 
Join Date: Jul 2012
Posts: 7,450
Oh sick, the pool is cantilevered out over the edge of the building. Very sexy.
     
     
  #1026  
Old Posted Dec 27, 2017, 4:23 AM
Bombardier Bombardier is offline
Registered User
 
Join Date: Aug 2016
Location: Chicago, IL
Posts: 467
That Indiana elevation is massive. Going to be cool when it is enclosed if they ever decide to order the glass!
     
     
  #1027  
Old Posted Dec 27, 2017, 7:26 AM
donnie's Avatar
donnie donnie is offline
Registered User
 
Join Date: Feb 2011
Posts: 596
Quote:
Originally Posted by LouisVanDerWright View Post
Oh sick, the pool is cantilevered out over the edge of the building. Very sexy.
That's crazy, i didn't realize what it was till you mentioned it! This might be another tower that looks better in life then on paper like OBP!
     
     
  #1028  
Old Posted Dec 27, 2017, 9:06 AM
KWillChicago's Avatar
KWillChicago KWillChicago is offline
Registered User
 
Join Date: Mar 2015
Location: Chicago
Posts: 1,115
Quote:
Originally Posted by LouisVanDerWright View Post
Oh sick, the pool is cantilevered out over the edge of the building. Very sexy.
I always dreamed of having an infinite pool on the roof of the trump. Aside from vegas, miami and l.a. I dont think i've heard of cool pools on skyscrapers in the US. Im sure thier out there though.
     
     
  #1029  
Old Posted Dec 27, 2017, 9:59 AM
donnie's Avatar
donnie donnie is offline
Registered User
 
Join Date: Feb 2011
Posts: 596
I wonder if the extreme cold has any effect on the concrete and does it take longer to cure and if so how much slower or faster does construction move?
     
     
  #1030  
Old Posted Dec 27, 2017, 3:20 PM
Notyrview Notyrview is offline
BANNED
 
Join Date: Dec 2012
Location: New York City
Posts: 1,648
Someone might need to clarify, but i’m pretty sure it doesn’t matter. I remember us talking about it when they poured Trump bc surprise it was barbarically cold then too.
     
     
  #1031  
Old Posted Dec 27, 2017, 3:29 PM
Bombardier Bombardier is offline
Registered User
 
Join Date: Aug 2016
Location: Chicago, IL
Posts: 467
Quote:
Originally Posted by KWillChicago View Post
I always dreamed of having an infinite pool on the roof of the trump. Aside from vegas, miami and l.a. I dont think i've heard of cool pools on skyscrapers in the US. Im sure thier out there though.
The winter garden at Essex will have an infinity edge pool looking over Lake Michigan. I believe it will be the first in a commercial application in Chicago, but I could be wrong.
     
     
  #1032  
Old Posted Dec 27, 2017, 3:36 PM
Bombardier Bombardier is offline
Registered User
 
Join Date: Aug 2016
Location: Chicago, IL
Posts: 467
Quote:
Originally Posted by donnie View Post
I wonder if the extreme cold has any effect on the concrete and does it take longer to cure and if so how much slower or faster does construction move?
Cold temperatures are addressed with set accelerating admixtures in the concrete mix, natural gas heaters under the working deck (which is why you see the white plastic draped under the deck before the pour), and concrete blankets over the top of the pour usually just at the edges. You do not want the temperature of the concrete to change from warm to cold too quickly or it will crack.

However, the frigid temperatures of the last 2 days have effectively shut down concrete operations across the city. The men don't want to work in subzero wind chills.
     
     
  #1033  
Old Posted Dec 29, 2017, 3:03 PM
SamInTheLoop SamInTheLoop is offline
you know where I'll be
 
Join Date: Sep 2006
Posts: 5,543
Quote:
Originally Posted by ithakas View Post
2090 by my rough count (Essex, OGP, SoMi, 1136 S. Wabash).

Also, 1411 S Michigan: ~200 units delivering in 2018.....
__________________
It's simple, really - try not to design or build trash.
     
     
  #1034  
Old Posted Dec 29, 2017, 3:04 PM
SamInTheLoop SamInTheLoop is offline
you know where I'll be
 
Join Date: Sep 2006
Posts: 5,543
[QUOTE=LouisVanDerWright;8029516]Oh sick, the pool is cantilevered out over the edge of the building. Very sexy.[/QUOTE

That is a nice little surprise....
__________________
It's simple, really - try not to design or build trash.
     
     
  #1035  
Old Posted Dec 29, 2017, 3:05 PM
SamInTheLoop SamInTheLoop is offline
you know where I'll be
 
Join Date: Sep 2006
Posts: 5,543
Quote:
Originally Posted by left of center View Post
^ 130 N Franklin is the long shot project I'm really hoping materializes in this boom.
Mine as well.....
__________________
It's simple, really - try not to design or build trash.
     
     
  #1036  
Old Posted Dec 29, 2017, 10:04 PM
spyguy's Avatar
spyguy spyguy is offline
THAT Guy
 
Join Date: Oct 2005
Posts: 5,949
Wow, Sam is back? It's a Festivus miracle.
     
     
  #1037  
Old Posted Dec 29, 2017, 11:26 PM
BVictor1's Avatar
BVictor1 BVictor1 is offline
Registered User
 
Join Date: Sep 2002
Location: Chicago
Posts: 10,416
12/29/17













__________________
titanic1
     
     
  #1038  
Old Posted Dec 30, 2017, 12:19 AM
donnie's Avatar
donnie donnie is offline
Registered User
 
Join Date: Feb 2011
Posts: 596
Looking at page 1,Is that a blow hole floor at around the 50th floor much like Vista is using?
Thnx in advance...
     
     
  #1039  
Old Posted Dec 30, 2017, 3:56 AM
BVictor1's Avatar
BVictor1 BVictor1 is offline
Registered User
 
Join Date: Sep 2002
Location: Chicago
Posts: 10,416
Quote:
Originally Posted by donnie View Post
Looking at page 1,Is that a blow hole floor at around the 50th floor much like Vista is using?
Thnx in advance...
Nope.

Floors 49-50 are amenities floors. That corner will be open space with a fire pit.
__________________
titanic1
     
     
  #1040  
Old Posted Dec 30, 2017, 1:21 PM
BVictor1's Avatar
BVictor1 BVictor1 is offline
Registered User
 
Join Date: Sep 2002
Location: Chicago
Posts: 10,416
A few more...

12/29/17







Approaching the first setback along the eastern flank. Another two or so floor to go before that mark is met.




__________________
titanic1
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
 

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture > Completed Project Threads Archive
Forum Jump



Forum Jump


All times are GMT. The time now is 12:49 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.