Quote:
Originally Posted by BonoboZill4
I'd say June or July if we are looking at 1.5 floors per week as safe bets. The core could definitely top out in May. i wouldn't be surprised if the glass catches up to the floors by April and has to slow down even.
Either way, early Summer for sure 
|
I think you are right on the structure. There are around 21 working days/mo - at 3 days/floor that is about 4 and a half months. Add in some weather days and holidays, plus a little more time for the top floors that always take a little longer, and I would say concrete would be wrapped up before the 4th of July with any luck.
It would be tough to see the glass catching up much more unless they add another setting crew... they look to also be on a 3 day cycle which is moving pretty good for curtainwall.
In any case, this project is moving along very well... glass looks pretty good to IMHO.