  #141  
Old Posted Dec 14, 2019, 1:15 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
12/13.

South core has jumped again. Now fully above street level along with the north core. I believe they will likely jump the cranes before they jump the north core again. Looks like the north crane would only just barely clear the pump boom on the north core once it goes up another level.



     
     
  #142  
Old Posted Dec 18, 2019, 1:00 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
12/17.

Happened to catch them lifting the pump boom for the south core in to place.

The entire site is now up to at least the 2nd garage level.







     
     
  #143  
Old Posted Dec 27, 2019, 1:39 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
12/26.

Second garage level is complete across the whole site. Big pour on the top garage level today. You can see that the curved walls for the valet ramp are in at the NW corner.



     
     
  #144  
Old Posted Dec 31, 2019, 10:25 PM
MN/WI MN/WI is offline
Registered User
 
Join Date: Jun 2014
Posts: 436
See no one comes here.
     
     
  #145  
Old Posted Jan 1, 2020, 3:32 PM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
12/31.

First formwork for the plaza level is going up along the north side of the site.



     
     
  #146  
Old Posted Jan 3, 2020, 11:52 PM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
1/3.



     
     
  #147  
Old Posted Jan 10, 2020, 1:26 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
1/9.

Looks like they're getting pretty close to jumping the north core again. Again, I think the cranes need to jump as well before the cores can go up any further. Crane jumps coming this weekend maybe? First portion of the plaza looks like it should be poured soon as well.




Last edited by MPLS_Const_Watch; Jan 10, 2020 at 1:50 AM.
     
     
  #148  
Old Posted Jan 14, 2020, 11:44 PM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
1/14.

North core has jumped.



     
     
  #149  
Old Posted Jan 24, 2020, 1:28 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
1/23.

Final big pour for the third garage level completed today. South core is now up to the 2nd level above grade as well.



     
     
  #150  
Old Posted Jan 31, 2020, 2:42 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
1/30.



     
     
  #151  
Old Posted Feb 5, 2020, 12:13 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
2/4.

First plaza pour today!



     
     
  #152  
Old Posted Feb 14, 2020, 12:27 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
2/13.

North core has jumped again. The entire site is now up to plaza level. First columns for the first floor above grade were poured today. They must be jumping these cranes soon. They've had to fold the north concrete boom down to avoid hitting it with the crane.



     
     
  #153  
Old Posted Feb 15, 2020, 1:44 AM
colemonkee's Avatar
colemonkee colemonkee is offline
Ridin' into the sunset
 
Join Date: Nov 2004
Location: Los Angeles
Posts: 9,097
People visit the page, just not a lot of comments. But this is exciting as it's one of the taller towers to be built in Minneapolis in some time. This should get interesting now that they are at grade. Looks like they are continuing with steel-reinforced concrete, and not steel beams, which is interesting as this has a pretty significant office component to it.
__________________
"Then each time Fleetwood would be not so much overcome by remorse as bedazzled at having been shown the secret backlands of wealth, and how sooner or later it depended on some act of murder, seldom limited to once."

Against the Day, Thomas Pynchon
     
     
  #154  
Old Posted Feb 15, 2020, 2:28 PM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
Quote:
Originally Posted by colemonkee View Post
But this is exciting as it's one of the taller towers to be built in Minneapolis in some time.
Yes, this project and Eleven (http://forum.skyscraperpage.com/showthread.php?t=232913) are the two tallest buildings to be built in Minneapolis since Capella Tower (http://skyscraperpage.com/cities/?buildingID=2491) was completed 28 years ago!
     
     
  #155  
Old Posted Feb 17, 2020, 3:04 AM
kenratboy kenratboy is offline
Registered User
 
Join Date: Nov 2003
Location: Salt Lake City, UT
Posts: 1,096
Great to see the progress. The weather is improving, and it will only speed things up. Very exciting! Agree with the earlier comments, not a lot of exciting stuff happening.

I work south of downtown in a tall building and have a perfect view of the skyline. Really needs some more love!
     
     
  #156  
Old Posted Feb 19, 2020, 12:38 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
2/18.

North crane and south core have both jumped.

     
     
  #157  
Old Posted Feb 22, 2020, 2:56 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
2/21.

Lots of 1st floor columns up now, first sections of form work for the 2nd floor in place. Sections of small trusses on site that appear likely to be used to increase the height of the mini crane?












Last edited by MPLS_Const_Watch; Feb 22, 2020 at 11:39 PM.
     
     
  #158  
Old Posted Mar 2, 2020, 11:22 PM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
3/2.

North core jumped, now up to 4th floor. Mini crane also raised.











     
     
  #159  
Old Posted Mar 6, 2020, 12:37 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
3/5.



     
     
  #160  
Old Posted Jul 31, 2020, 5:28 AM
MPLS_Const_Watch MPLS_Const_Watch is offline
Registered User
 
Join Date: Mar 2018
Posts: 678
7/30.







Skyway footings going in across the street for the library connection:

     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
 

Go Back   SkyscraperPage Forum > Discussion Forums > Buildings & Architecture > Completed Project Threads Archive
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 8:28 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.