Old Posted Apr 9, 2015, 6:37 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
MIAMI | M Tower (56 SW 1st Street) | 605 FT | 57 FLOORS

52-Story Tower Above MPA Garage With 432 Rental Units In The Works







Quote:
A residential tower that would rise above an existing parking garage in downtown Miami is being prepared for submission to Miami’s Planning Department for review.

In 2013, the Miami Parking Authority board approved a deal with Downtown 56, LLC to redevelop the garage, located at 70 SW First St. The garage is known as the Cultural Center Garage, or Garage 2. It sits on a 28,910-square-foot lot, while Downtown 56 owns an adjacent property sized at about 17,000-square-feet.

As part of the project, a 52-story tower with 432 rental units is planned for the empty lot. The garage is to be restored, refurbished, and brought up to code, while adding additional spaces and ground-floor retail.

Submission to the city is expected within the next ‘couple of months’, an MPA official told TNM. Once approved, construction is expcted to take 36 months.

Zyscovich is the project architect.
==========================
http://www.thenextmiami.com/index.ph...-rental-units/

Last edited by chris08876; Jul 19, 2022 at 1:42 AM.
Reply With Quote
     
     
  #2  
Old Posted Apr 9, 2015, 8:41 PM
bobdreamz's Avatar
bobdreamz bobdreamz is online now
Registered User
 
Join Date: Mar 2002
Location: Miami/Orlando, FL.
Posts: 8,123
Well it certainly beats this ugly garage in its current form:



Another residential 500+ footer in the heart of downtown and right near the Metrorail & Metromover!
__________________
Miami : 62 Skyscrapers over 500+ Ft.|150+ Meters | 14 Under Construction.

Last edited by bobdreamz; Apr 9, 2015 at 10:22 PM.
Reply With Quote
     
     
  #3  
Old Posted Apr 9, 2015, 8:43 PM
colemonkee's Avatar
colemonkee colemonkee is offline
Ridin' into the sunset
 
Join Date: Nov 2004
Location: Los Angeles
Posts: 9,093
The sheer volume of development going on in Miami at the moment is truly astounding. And while the location near the Metro Mover is spot on and this is definitely an improvement over the existing structure, the tower design on this is pretty bad and should be sent back to the drawing board.
__________________
"Then each time Fleetwood would be not so much overcome by remorse as bedazzled at having been shown the secret backlands of wealth, and how sooner or later it depended on some act of murder, seldom limited to once."

Against the Day, Thomas Pynchon
Reply With Quote
     
     
  #4  
Old Posted Apr 9, 2015, 8:46 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
This is still early though. It may undergo a design change like many projects during this stage. Usually what winds up happening is that it will go to the commission, get an early approval, and then we will see them tinker with it. While I don't expect this project to change dramatically, it will most likely look different based on the trend of designs getting modifications through the approval and permitting process. The height is also something that will be okay with the FAA. They recently in the past months approved a flurry of 500 + footers. Many starting construction too recently.
Reply With Quote
     
     
  #5  
Old Posted Apr 9, 2015, 10:02 PM
bobdreamz's Avatar
bobdreamz bobdreamz is online now
Registered User
 
Join Date: Mar 2002
Location: Miami/Orlando, FL.
Posts: 8,123
Quote:
Originally Posted by chris08876 View Post
This is still early though. It may undergo a design change like many projects during this stage. Usually what winds up happening is that it will go to the commission, get an early approval, and then we will see them tinker with it. While I don't expect this project to change dramatically, it will most likely look different based on the trend of designs getting modifications through the approval and permitting process.The height is also something that will be okay with the FAA. They recently in the past months approved a flurry of 500 + footers. Many starting construction too recently.
The height should be fine since the Miami-Dade Gov't. Center is about 2 blocks north from this proposal and it stands at 510 feet.

__________________
Miami : 62 Skyscrapers over 500+ Ft.|150+ Meters | 14 Under Construction.
Reply With Quote
     
     
  #6  
Old Posted Apr 10, 2015, 1:28 AM
bobdreamz's Avatar
bobdreamz bobdreamz is online now
Registered User
 
Join Date: Mar 2002
Location: Miami/Orlando, FL.
Posts: 8,123
Apparently this deal goes back to May of 2013 with the developer & the City of Miami:

City Garage Getting 47 story Crown.
Written by Meisha Perrin on May 9, 2013

Forty-seven stories of residences, offices and amenities totaling 415,000 square feet will rise atop a Miami Parking Authority seven-story downtown garage between 56 and 70 SW First St. — while the garage itself will also be upgraded.

Last week the authority approved a proposal from Downtown 56 LLC to redevelop the garage, which the board agreed in April needed renovation.

Now, the company is set to restore the garage to adhere to Florida’s 2010 building code and to make it more aesthetically pleasing, said authority CEO Art Noriega, in addition to building a 54-story, $73 million tower.

Structurally, he said, the garage is in good shape. The problem is code and aesthetics.


Read more : http://www.miamitodaynews.com/news/130509/story7.shtml
__________________
Miami : 62 Skyscrapers over 500+ Ft.|150+ Meters | 14 Under Construction.
Reply With Quote
     
     
  #7  
Old Posted Apr 10, 2015, 2:57 AM
dave8721 dave8721 is offline
Registered User
 
Join Date: Jul 2005
Location: Miami
Posts: 4,036
Glad to hear this project is still around. It had been 2 years since we'd heard from it and I had feared it was dead. Definitely a good re-use of an old out-dated parking garage. I have no problem with the design not being ground breaking. Its a rental. Probably non-luxury. Something we need a lot more of. The western side of the old CBD is the place for it too.

Now if we can just get rid of those spaghetti i-95 ramps...
Reply With Quote
     
     
  #8  
Old Posted Apr 10, 2015, 2:59 AM
dave8721 dave8721 is offline
Registered User
 
Join Date: Jul 2005
Location: Miami
Posts: 4,036
Quote:
Originally Posted by bobdreamz View Post
The height should be fine since the Miami-Dade Gov't. Center is about 2 blocks north from this proposal and it stands at 510 feet.
And All Aboard Fl is going for 1000+ feet across the street from Government Center.
Reply With Quote
     
     
  #9  
Old Posted Jun 6, 2015, 2:25 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
I think the garage is still there. Wonder when this will start up.
Reply With Quote
     
     
  #10  
Old Posted Jun 7, 2016, 9:59 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
53-Story M Tower Submitted For UDRB Review

Quote:
Downtown 56, LLC is moving forward with plans to develop a 53-story mixed-use building called M Tower in downtown Miami.

The developer submitted plans late last month for the project to Miami’s Urban Development Review Board. The board meeting to review the project is scheduled for next week.

According to the plans prepared by architect Zyscovich, the 628-foot tower is to include 440 residential units, 25,000 square feet of office space, and ground floor retail.

The project is proposed as part of the redevelopment of the Miami Parking Authority Cultural Center Garage at 70 Southwest First St. Downtown 56 owns adjacent land and was selected as the winning bidder after an RFP from the MPA.

Downtown 56 lists Jorge Brugo of Axis Realty Trust (a principal behind the Pi Art Tech bid for Miami Dade College’s 520 Biscayne) as a contact.

Credit: NXT
Reply With Quote
     
     
  #11  
Old Posted Jan 20, 2018, 1:45 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
MIAMI | M Tower (70 SW First Street) | 629 FT | 53 FLOORS


= = = = = = = =

M-Tower Developer Applies For Warrant From Planning Department

Quote:
Downtown 56 LLC has applied for approval with Miami’s Planning Department for a warrant that would allow M-Tower to be built.

The application was submitted yesterday, January 17. Approval cannot be granted before February 9 under zoning law.

If approved, the 53-story would rise 629 feet atop a Miami Parking Authority garage.

The tower is proposed to include 440 residential units, along with parking, and a small amount of office and retail.

Zyscovich is the architect.
==============================
NXT

Last edited by chris08876; Jan 20, 2018 at 6:26 PM. Reason: update title to reflect marketing name with address
Reply With Quote
     
     
  #12  
Old Posted Jan 20, 2018, 6:23 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
Extra Rendering:


Credit: NXT
Reply With Quote
     
     
  #13  
Old Posted Jan 20, 2018, 6:25 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
Reply With Quote
     
     
  #14  
Old Posted May 14, 2022, 12:42 AM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
Total Demolition Permit Submitted For 7-Story Downtown Miami Parking Garage



Quote:
A 7-story parking garage in downtown Miami is set for total demolition, according to a permit application filed with Miami’s Building Department this morning.

The garage is operated by the Miami Parking Authority. There are plans to replace it with a 49-story tower that will have an even bigger parking garage.

According to the demolition permit application submitted on May 12, a total of 124,304 square feet will be demolished at an estimated cost of $300,000. A contractor is not yet attached to the permit.

Lions Group presented plans last year to an MPA Board to combine the garage site with property it owns next door to build the 49-story project called M-Tower.

According to preliminary plans submitted last year, M-Tower is proposed to include:

624 residential units
residential amenities
ground floor retail, and offices for the MPA
717 parking spaces (replacing the existing 658-space garage)
The plans were prepared by architectural firm NBWW.

There does not yet appear to be a construction permit pending for the new tower.
===================
NXT
Reply With Quote
     
     
  #15  
Old Posted Jul 5, 2022, 5:58 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
Looks like demo will occur within the next few months. Project is moving forward.
Reply With Quote
     
     
  #16  
Old Posted Jul 5, 2022, 6:26 PM
JMKeynes JMKeynes is offline
BANNED
 
Join Date: Aug 2017
Location: SW3
Posts: 4,216
Lame!!!
Reply With Quote
     
     
  #17  
Old Posted Aug 29, 2022, 5:24 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
Downtown Miami’s M Tower Submitted To FAA At 605 Feet, Cranes To Rise 705 Feet

Quote:
Plans for downtown Miami’s M Tower were submitted to the Federal Aviation Administration on August 23.

Both the permanent height of the tower and temporary construction cranes are now being reviewed by the agency.

M Tower is planned to have a permanent height of 605 feet above ground, or 615 feet above sea level, the filing states.


Temporary tower construction cranes are planned to reach a height of 705 feet above ground, or 715 feet above sea level, according to the filing. The work schedule for the cranes is estimated to run from March 1, 2023 to December 1, 2024.

The permanent podium height at M Tower is listed at 109 feet.

According to plans from last year, M Tower was planned to rise 49 stories and include:

624 residential units, along with amenities
ground floor retail, and offices for the MPA
717 parking spaces (replacing the existing 658-space garage)
A demolition permit was applied for in May.
==================
NXT
Reply With Quote
     
     
  #18  
Old Posted Oct 4, 2022, 1:56 AM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
Demo expected within 1 to 2 months.
Reply With Quote
     
     
  #19  
Old Posted Oct 27, 2022, 1:28 AM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
Construction Permit Submitted For 650-Foot M-Tower, Contractor Named



Quote:
Downtown Miami’s M-Tower has moved into the construction permitting phase.

According to Miami Building Department records, an application for a construction permit to build the tower was filed on October 24.

The filing states that the tower will rise approximately 56 stories, or 650 feet.

M-Tower will have 675 living units, the permit filing says.

A filing with the UDRB earlier this year showed the project would also have 694 parking spaces and 10,531 square feet of commercial.

Total hard construction cost is estimated at $191,710,751.

Balfour Beatty is listed as the contractor. Downtown 1st Street LLC of Great Neck, New York is listed as the owner.

The full construction plans have not yet been filed, so review is not yet underway.

A tree permit was also applied for on the same day.

A demolition permit was applied for in May, and is still being reviewed.
=====================
NXT
Reply With Quote
     
     
  #20  
Old Posted Oct 15, 2023, 4:29 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,694
Demo in progress.





Credit: volvoshine
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > Proposals
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 11:19 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.