These are the last two construction updates that the airport posted:
May 17, 2017
The first steel beam was erected May 17 for the South Concourse, signaling the start of vertical construction.
During the next 13-17 weeks, 21,600 tons of steel (an average of 30-40 tons per day) will be brought to the site for the South Concourse, Terminal and Gateway Center.
Directional signs for the new Park-and-Wait lot are being installed in preparation for a June 1 opening.
More than 400 construction workers are now on site.
May 31, 2017
New Park and Wait lot opens June 1, 2017.
Construction crews are building rebar cage towers (24’ high) for the parking garage and rebar cage columns (33’ high) for the elevated roadway.
Preparations are underway for North Concourse construction.
Work to extend existing tunnel to connect the South and North Concourses.
About 430 workers currently on site.
Concrete pours taking place for Terminal walls.