Old Posted Oct 13, 2022, 4:58 PM
Zapatan's Avatar
Zapatan Zapatan is offline
DENNAB
 
Join Date: Aug 2009
Location: NA - Europe
Posts: 6,080
Hell yea!
Reply With Quote
     
     
  #22  
Old Posted Nov 1, 2022, 4:55 PM
downtownNashville downtownNashville is offline
Registered User
 
Join Date: Jan 2021
Posts: 41
The Foundation permits have been issued for this project. The initial demolition permits have also been applied for, and the grading plans are approved. Looking good for this to start in the beginning of 2023.
Reply With Quote
     
     
  #23  
Old Posted Dec 3, 2022, 4:14 PM
downtownNashville downtownNashville is offline
Registered User
 
Join Date: Jan 2021
Posts: 41
Per the Nashville Post, Tony Giarratana has closed on the purchase of the property he needs to construct the tower. We've also had reports that the YMCA has closed the portion of the facility that will be demolished to make way for their new facility and Tony's tower. Looking like this is still on track for an early 2023 start.

Link to Article
Reply With Quote
     
     
  #24  
Old Posted Dec 3, 2022, 6:34 PM
Zapatan's Avatar
Zapatan Zapatan is offline
DENNAB
 
Join Date: Aug 2009
Location: NA - Europe
Posts: 6,080
Nashville's gonna be the next Austin, I swear.
Reply With Quote
     
     
  #25  
Old Posted Dec 13, 2022, 1:50 PM
downtownNashville downtownNashville is offline
Registered User
 
Join Date: Jan 2021
Posts: 41
Per UP, construction barriers are up, and heavy equipment is on site. It looks like demolition of the old YMCA is set to begin soon.
Reply With Quote
     
     
  #26  
Old Posted Dec 13, 2022, 2:29 PM
Dale Dale is offline
Registered User
 
Join Date: Dec 2001
Location: Charlotte
Posts: 4,802
Here we go!
Reply With Quote
     
     
  #27  
Old Posted Jan 1, 2023, 4:58 PM
downtownNashville downtownNashville is offline
Registered User
 
Join Date: Jan 2021
Posts: 41
Demolition of the old YMCA has commenced.
Reply With Quote
     
     
  #28  
Old Posted Feb 28, 2023, 9:22 PM
BnaBreaker's Avatar
BnaBreaker BnaBreaker is offline
Future God
 
Join Date: Jul 2001
Location: Chicago/Nashville
Posts: 19,540
A shell permit worth $89 million was issued for this project today. I'd say this can be moved into the Under Construction section now, no?
__________________
"Emancipate yourself from mental slavery. None but ourselves can free our minds."

-Bob Marley
Reply With Quote
     
     
  #29  
Old Posted Feb 28, 2023, 10:00 PM
futuresooner's Avatar
futuresooner futuresooner is offline
Registered User
 
Join Date: Nov 2007
Location: Austin, TX
Posts: 1,241
Quote:
Originally Posted by BnaBreaker View Post
A shell permit worth $89 million was issued for this project today. I'd say this can be moved into the Under Construction section now, no?
Once foundation work takes place, then it can be moved over.

I'm also shocked at the lack of overall Nashville development posting here.
__________________
"When you don't want to Dallas your Austin, you just emulate the Bay Area."
Reply With Quote
     
     
  #30  
Old Posted Mar 1, 2023, 12:50 AM
Dale Dale is offline
Registered User
 
Join Date: Dec 2001
Location: Charlotte
Posts: 4,802
Quote:
Originally Posted by futuresooner View Post
Once foundation work takes place, then it can be moved over.

I'm also shocked at the lack of overall Nashville development posting here.
Seems like they’re all on UP.
Reply With Quote
     
     
  #31  
Old Posted Mar 1, 2023, 2:15 PM
downtownNashville downtownNashville is offline
Registered User
 
Join Date: Jan 2021
Posts: 41
Per the blasting permit that was recently issued, they are to begin blasting sometime in March.
Reply With Quote
     
     
  #32  
Old Posted Apr 4, 2023, 9:31 PM
downtownNashville downtownNashville is offline
Registered User
 
Join Date: Jan 2021
Posts: 41
Blasting has started per picture posted on UP.
Reply With Quote
     
     
  #33  
Old Posted Apr 18, 2023, 7:28 PM
ILUVSAT's Avatar
ILUVSAT ILUVSAT is offline
May the Schwartz be w/ U!
 
Join Date: Sep 2013
Location: Nomadic
Posts: 1,734
Quote:
Originally Posted by BnaBreaker View Post
A shell permit worth $89 million was issued for this project today. I'd say this can be moved into the Under Construction section now, no?
That's great news...and the blasting too.

But, $89 million for the shell? Seems low compared to other buildings of this magnitude.
Reply With Quote
     
     
  #34  
Old Posted Apr 26, 2023, 5:15 PM
H-TownPM H-TownPM is offline
Registered User
 
Join Date: Mar 2023
Posts: 2
I've heard this job has gone out for rebid.

Also, what is this UP you all speak of? I'm new to the forum.
Reply With Quote
     
     
  #35  
Old Posted Apr 26, 2023, 9:02 PM
nashvilleron nashvilleron is offline
Registered User
 
Join Date: Sep 2012
Posts: 95
Quote:
Originally Posted by H-TownPM View Post
I've heard this job has gone out for rebid.

Also, what is this UP you all speak of? I'm new to the forum.

It should be easy enough to find out if it has as either myself or co-worker will reach out to Tony.

I never bother him unless it is something major, but I do have his number and email.

Always like to put rumors to rest if they are false but confirm if true. I do know that finish out permits were issued all the way through floor 40 and if they are rebidding it may be some subcontractor. The main contractor is building two other buildings for Giarratana right next door and across the street, not to mention the YMCA connected to this building.
Reply With Quote
     
     
  #36  
Old Posted May 25, 2023, 9:44 PM
H-TownPM H-TownPM is offline
Registered User
 
Join Date: Mar 2023
Posts: 2
Quote:
Originally Posted by nashvilleron View Post
It should be easy enough to find out if it has as either myself or co-worker will reach out to Tony.

I never bother him unless it is something major, but I do have his number and email.

Always like to put rumors to rest if they are false but confirm if true. I do know that finish out permits were issued all the way through floor 40 and if they are rebidding it may be some subcontractor. The main contractor is building two other buildings for Giarratana right next door and across the street, not to mention the YMCA connected to this building.

Confirmed with Giarratana that Brasfield & Gorrie has the contract now, although not sure when they plan on going vertical.
Reply With Quote
     
     
  #37  
Old Posted Jul 23, 2023, 4:32 PM
downtownNashville downtownNashville is offline
Registered User
 
Join Date: Jan 2021
Posts: 41
Per a picture from UP, work on the first crane base has started.
Reply With Quote
     
     
  #38  
Old Posted Jul 27, 2023, 7:59 AM
futuresooner's Avatar
futuresooner futuresooner is offline
Registered User
 
Join Date: Nov 2007
Location: Austin, TX
Posts: 1,241
Quote:
Originally Posted by downtownNashville View Post
Per a picture from UP, work on the first crane base has started.
Thar she be!
__________________
"When you don't want to Dallas your Austin, you just emulate the Bay Area."
Reply With Quote
     
     
  #39  
Old Posted Jul 27, 2023, 10:39 AM
The ATX's Avatar
The ATX The ATX is offline
Moderator
 
Join Date: May 2006
Location: Where the lights are much brighter
Posts: 12,052
Nice! It's great to see this one getting underway.
__________________
Follow The ATX on X:
https://twitter.com/TheATX1

Things will be great when you're downtown.
Reply With Quote
     
     
  #40  
Old Posted Jul 27, 2023, 12:55 PM
downtownNashville downtownNashville is offline
Registered User
 
Join Date: Jan 2021
Posts: 41
Quote:
Originally Posted by futuresooner View Post
Thar she be!
Yep! An interesting fact about this picture is that the developer of this tower built 5 of the 7 buildings in this shot.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > Skyscraper & Highrise Construction
Forum Jump



Forum Jump


All times are GMT. The time now is 11:22 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.