  #3101  
Old Posted Jul 15, 2022, 6:34 AM
rivernorthlurker rivernorthlurker is offline
Registered User
 
Join Date: Dec 2018
Location: Chicago
Posts: 1,107
Quote:
Originally Posted by AusTex View Post
Any timeline for the first piece of glass to be installed? It is looking like it is not too distant in the future for this beauty.
Curious how the windows go as windows have been delayed due to supply chain issues on a lot of projects nationwide.
Reply With Quote
     
     
  #3102  
Old Posted Jul 15, 2022, 4:05 PM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 51,899
At this point, I’d take seeing even a mockup. I just want to know the exact tone this tower will have.
__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
Reply With Quote
     
     
  #3103  
Old Posted Jul 16, 2022, 7:06 PM
JMKeynes JMKeynes is offline
BANNED
 
Join Date: Aug 2017
Location: SW3
Posts: 4,216
Xing,

Someone posted this photo on YIMBY. Can you add in 270 and 175 Park? 520 Fifth too.

Reply With Quote
     
     
  #3104  
Old Posted Jul 16, 2022, 7:35 PM
JACKinBeantown's Avatar
JACKinBeantown JACKinBeantown is offline
JACKinBeantown
 
Join Date: Jun 2003
Location: Location: Location:
Posts: 8,847
Quote:
Originally Posted by JMKeynes View Post
Xing,

Someone posted this photo on YIMBY. Can you add in 270 and 175 Park? 520 Fifth too.
What's the magic word?
__________________
Hi.
Reply With Quote
     
     
  #3105  
Old Posted Jul 18, 2022, 5:15 PM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 51,899
Diverted diagram concerns to the appropriate thread…
https://skyscraperpage.com/forum/sho...d.php?t=251347
__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
Reply With Quote
     
     
  #3106  
Old Posted Jul 18, 2022, 5:58 PM
NYguy's Avatar
NYguy NYguy is offline
New Yorker for life
 
Join Date: Jul 2001
Location: Borough of Jersey
Posts: 51,899
Checking in on cam…















__________________
NEW YORK is Back!

“Office buildings are our factories – whether for tech, creative or traditional industries we must continue to grow our modern factories to create new jobs,” said United States Senator Chuck Schumer.
Reply With Quote
     
     
  #3107  
Old Posted Jul 18, 2022, 8:53 PM
Lincolnlover2005's Avatar
Lincolnlover2005 Lincolnlover2005 is offline
Registered User
 
Join Date: Jun 2019
Posts: 135
Quote:
Originally Posted by NYguy View Post
Checking in on cam…















Ooh first setback¡!!!
Reply With Quote
     
     
  #3108  
Old Posted Jul 18, 2022, 8:59 PM
AusTex's Avatar
AusTex AusTex is offline
Registered User
 
Join Date: May 2007
Location: Austin
Posts: 631
Quote:
Originally Posted by NYguy View Post
At this point, I’d take seeing even a mockup. I just want to know the exact tone this tower will have.
I agree with you. Why the wait? We are lucky in Austin with our 1,022'er. We are at Site Prep; concrete is just about ready to pour and we already have a mock-up with three colors of glass, piping and mullions. I'm not sure if the tower will have all three hues of the glass, but it sure is nice to see the mock-up on site.

The wait for 270 Park Ave. is getting frustrating!
Reply With Quote
     
     
  #3109  
Old Posted Jul 18, 2022, 9:18 PM
JACKinBeantown's Avatar
JACKinBeantown JACKinBeantown is offline
JACKinBeantown
 
Join Date: Jun 2003
Location: Location: Location:
Posts: 8,847
Quote:
Originally Posted by AusTex View Post

The wait for 270 Park Ave. is getting frustrating!
Huh? It's actually going up pretty fast.
__________________
Hi.
Reply With Quote
     
     
  #3110  
Old Posted Jul 19, 2022, 1:56 AM
TheBigAPPLE TheBigAPPLE is offline
Registered User
 
Join Date: Jul 2022
Posts: 1
Guys, the facade will start soon. Sometime around early-mid August. As you can see also the fireproofing on the first and second office floors are done, once those are done you'll see the facade. Also, we are at the last floor level before the first setback. Every setback will make this tower speed faster due to less floor plates towards the top.
Reply With Quote
     
     
  #3111  
Old Posted Jul 19, 2022, 3:02 AM
JMKeynes JMKeynes is offline
BANNED
 
Join Date: Aug 2017
Location: SW3
Posts: 4,216
Quote:
Originally Posted by TheBigAPPLE View Post
Guys, the facade will start soon. Sometime around early-mid August. As you can see also the fireproofing on the first and second office floors are done, once those are done you'll see the facade. Also, we are at the last floor level before the first setback. Every setback will make this tower speed faster due to less floor plates towards the top.
Thanks! How many feet tall do you think it will be by the end of the year?
Reply With Quote
     
     
  #3112  
Old Posted Jul 19, 2022, 8:49 AM
TKD's Avatar
TKD TKD is offline
March Forward
 
Join Date: Mar 2022
Posts: 53
The fireproofing being done on said floors doesn't really equate to façade installation. Facade installation can occur whenever, some buildings don't install cladding until fully fire proof, but for comparable buildings like One Vanderbilt and One WTC, cladding was not installed until fireproofing had reached the 8th & 6th floors (respectively). A mid August date is plausible with this building having reached that point in the future but there is never a fully understood time table for cladding. But cladding installation is not what people are commenting on, they are commenting on not seeing a façade mock up.

Also, construction is not on the last floor before the setback, there are still 2 more floors, the third being the setback itself.
Reply With Quote
     
     
  #3113  
Old Posted Jul 19, 2022, 11:51 AM
mrnyc mrnyc is offline
cle/west village/shaolin
 
Join Date: Jul 2006
Posts: 11,723
i had to go up to midtown, so ...


Reply With Quote
     
     
  #3114  
Old Posted Jul 19, 2022, 12:07 PM
JMKeynes JMKeynes is offline
BANNED
 
Join Date: Aug 2017
Location: SW3
Posts: 4,216
Quote:
Originally Posted by mrnyc View Post
i had to go up to midtown, so ...


Xing,

Can you add the full 270 to this? Would 175 work too?
Reply With Quote
     
     
  #3115  
Old Posted Jul 19, 2022, 12:50 PM
Xing Lin's Avatar
Xing Lin Xing Lin is offline
Sydney
 
Join Date: Jul 2011
Posts: 171
Happy to match my 270 model into that shot, if it's alright with mrnyc! 175 would be obscured on the other side of MetLife from One Vandy there. Incidentally, I've just done a rendering from a similar angle on Park Ave, using a 2018 rendering by Adamson Associates:

Last edited by Xing Lin; Jul 23, 2022 at 1:53 PM.
Reply With Quote
     
     
  #3116  
Old Posted Jul 19, 2022, 1:39 PM
JMKeynes JMKeynes is offline
BANNED
 
Join Date: Aug 2017
Location: SW3
Posts: 4,216
Very nice work, Xing!
Reply With Quote
     
     
  #3117  
Old Posted Jul 19, 2022, 1:53 PM
JMKeynes JMKeynes is offline
BANNED
 
Join Date: Aug 2017
Location: SW3
Posts: 4,216
Can you put 175 and 270 in this one too?

Reply With Quote
     
     
  #3118  
Old Posted Jul 19, 2022, 3:18 PM
JACKinBeantown's Avatar
JACKinBeantown JACKinBeantown is offline
JACKinBeantown
 
Join Date: Jun 2003
Location: Location: Location:
Posts: 8,847
Quote:
Originally Posted by jmkeynes View Post
thanks! How many feet tall do you think it will be by the end of the year?
731
__________________
Hi.
Reply With Quote
     
     
  #3119  
Old Posted Jul 19, 2022, 3:21 PM
mrnyc mrnyc is offline
cle/west village/shaolin
 
Join Date: Jul 2006
Posts: 11,723
of course go for it xing -- but it looks like you pretty much already did!

if it helps i was up the steps on the north corner of 299 park, so a little bit of an elevated view.
Reply With Quote
     
     
  #3120  
Old Posted Jul 19, 2022, 4:21 PM
JMKeynes JMKeynes is offline
BANNED
 
Join Date: Aug 2017
Location: SW3
Posts: 4,216
Xing,

Could you fix 1 Vandy and Steinway too?
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > Supertall Construction
Forum Jump



Forum Jump


All times are GMT. The time now is 5:24 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.