  #61  
Old Posted May 24, 2022, 2:40 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 42,942
Signature Bridge Highway Project Anticipated Completion Pushed Back To 2026, Cost Rising



Quote:
The massive highway rebuild and expansion currently underway in the downtown Miami area is now estimated to be completed much later than originally announced, and at a higher cost, according to the project website.

The new completion date is anticipated for summer 2026 (compared to the original fall 2023). The new budget is estimated at $840 million (it was initially $802 million).

The contract began in October 2018, with a four-year deadline to the contractor for completion.

The deadline was permitted to be extended for special events, holidays, or weather delays.

Special events include events at the Arsht Center, American Airlines Arena, Bayfront Park and Marlins Park. Other events such as the Super Bowl, Art Basel, the South Beach Wine and Food Festival, the International Boat Show, and the Miami Marathon are also allowed to push back the deadline.

In addition to a Signature Bridge with spider or fountain-like arches, the project also includes rebuilding and expanding the highway in the area, including a double-deck highway.
===================
NXT
Reply With Quote
     
     
  #62  
Old Posted Jul 4, 2022, 2:02 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 42,942

Credit: volvoshine
Reply With Quote
     
     
  #63  
Old Posted Jan 13, 2023, 5:37 PM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 42,942
Reply With Quote
     
     
  #64  
Old Posted Jan 16, 2023, 8:19 AM
SEFTA's Avatar
SEFTA SEFTA is offline
Philly Pholly
 
Join Date: Jan 2016
Posts: 1,047
A $BILLION VANITY BRIDGE is what this will be.
Adding no more lanes to the beach. I'm guessing a Lexus lane is coming.
A DOUBLE DECKER! How pleasant.
A $BILLION would have probably covered a transit line to the beach
I thought this was a boondoggle from the beginning predicting a $BILLION price tag.
Yes. It will be beautiful.
The area around it won't

https://www.youtube.com/watch?v=RUkWBvvMpAE
__________________
Smart Cities

Last edited by SEFTA; Jan 16, 2023 at 8:32 AM.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Global Projects & Construction > General Development
Forum Jump


Thread Tools
Display Modes

Forum Jump


All times are GMT. The time now is 6:35 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2023, vBulletin Solutions, Inc.