  #81  
Old Posted Oct 2, 2020, 1:48 AM
Acajack's Avatar
Acajack Acajack is offline
Gros Méchant Loup
 
Join Date: Aug 2006
Location: Province 2, Canadian Empire
Posts: 72,949
Quote:
Originally Posted by J.OT13 View Post
Side note: based on the rendering, it looks like they will be incorporating the façade on the corner of Eddy and Wright within the development.

I believe Acajack and I had a short discussion on this a few months ago. Don't remember which thread.
On this page:
https://skyscraperpage.com/forum/showthread.php?p=8953063&highlight=balcony#post8953063

Good news about the façade. I did not see that coming. I guess our city council isn't as guidoune as I thought it was when it comes to developers.
__________________
Loin des yeux, loin du coeur.
Reply With Quote
     
     
  #82  
Old Posted Oct 2, 2020, 1:46 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,304
Quote:
Originally Posted by Acajack View Post
On this page:
https://skyscraperpage.com/forum/showthread.php?p=8953063&highlight=balcony#post8953063

Good news about the façade. I did not see that coming. I guess our city council isn't as guidoune as I thought it was when it comes to developers.
Well done! Finding it with the word "balcony"
Reply With Quote
     
     
  #83  
Old Posted Oct 2, 2020, 3:24 PM
Acajack's Avatar
Acajack Acajack is offline
Gros Méchant Loup
 
Join Date: Aug 2006
Location: Province 2, Canadian Empire
Posts: 72,949
Quote:
Originally Posted by J.OT13 View Post
Well done! Finding it with the word "balcony"
My secret tricks have been exposed!
__________________
Loin des yeux, loin du coeur.
Reply With Quote
     
     
  #84  
Old Posted Mar 16, 2021, 8:07 PM
Acajack's Avatar
Acajack Acajack is offline
Gros Méchant Loup
 
Join Date: Aug 2006
Location: Province 2, Canadian Empire
Posts: 72,949
I was in the VH (VAY-ahsh as my kids say) recently, and they have a construction fence up on the site and have begun some demolition work.
__________________
Loin des yeux, loin du coeur.
Reply With Quote
     
     
  #85  
Old Posted Mar 16, 2021, 8:17 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,304
Before anyone gets to excited, it's for the mid-rise, not one of the 33 floor towers.



https://www.ledroit.com/affaires/epiceri...atineau-42c78cbc718d7afa72d5816db6ec3425
Reply With Quote
     
     
  #86  
Old Posted Mar 16, 2021, 11:42 PM
UrbOttawa UrbOttawa is offline
Registered User
 
Join Date: Oct 2014
Posts: 414
Reply With Quote
     
     
  #87  
Old Posted Mar 16, 2021, 11:50 PM
UrbOttawa UrbOttawa is offline
Registered User
 
Join Date: Oct 2014
Posts: 414
Reply With Quote
     
     
  #88  
Old Posted Mar 20, 2021, 8:54 PM
JimmyBoy JimmyBoy is offline
Registered User
 
Join Date: Nov 2015
Posts: 1
Le Droit just published an article which stipulates how Le Groupe Heafey started the demolition of these buildings without any permits.

The main points of the article is that while the city issued a demolition permit in August, which was conditional on the builder obtaining a construction permit, none had been issued yet. And so, once the work started, the city issued a stop work order on March 12th, which was ignored and then, meragaliously, a permit was obtained on March 17th.

https://www.ledroit.com/actualites/gatin...es-bois-feda701ca52c8e027c032fbd4fc5f3ab

A second article in Le Droit also serves to illustrate the dysfunction within le Bureau de l'urbanisme. While the Municipal regulations call for a permit to be issued within 20 days, the delay now ranges between 180 to 200 days which explains why Le Groupe Heafey took matters in their own hands.

https://www.ledroit.com/actualites/gatin...blondin-5cc5d0061a2a0f5cbb639fa5dc5fe77a
Reply With Quote
     
     
  #89  
Old Posted Mar 20, 2021, 11:25 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,428
Quote:
Originally Posted by JimmyBoy View Post
Le Droit just published an article which stipulates how Le Groupe Heafey started the demolition of these buildings without any permits.

The main points of the article is that while the city issued a demolition permit in August, which was conditional on the builder obtaining a construction permit, none had been issued yet. And so, once the work started, the city issued a stop work order on March 12th, which was ignored and then, meragaliously, a permit was obtained on March 17th.

https://www.ledroit.com/actualites/gatin...es-bois-feda701ca52c8e027c032fbd4fc5f3ab

A second article in Le Droit also serves to illustrate the dysfunction within le Bureau de l'urbanisme. While the Municipal regulations call for a permit to be issued within 20 days, the delay now ranges between 180 to 200 days which explains why Le Groupe Heafey took matters in their own hands.

https://www.ledroit.com/actualites/gatin...blondin-5cc5d0061a2a0f5cbb639fa5dc5fe77a
Great info. And welcome to the forum!
Reply With Quote
     
     
  #90  
Old Posted Mar 21, 2021, 3:37 AM
harls's Avatar
harls harls is offline
Mooderator
 
Join Date: Jan 2002
Location: Aylmer, Québec
Posts: 21,283
It's surprising how much power one man (Clennett) has over developers... or am I missing something?
Reply With Quote
     
     
  #91  
Old Posted Jun 29, 2021, 8:30 PM
PhilJones PhilJones is offline
Registered User
 
Join Date: Jun 2021
Location: Ile-de-Hull, Quebec, Canada
Posts: 2
The demolition of those buildings and construction of the new building are happening right outside my balcony (I'm in Le W/E Phase I). I've been documenting it since the first time I spotted fire fighters hacking at the old apartment building there.
They started blasting today.
Here's an album that I'm keeping updated, including the mockups I found in this thread (thanks!) and some historical context for the site. The destruction of the apartment building was particularly dramatic.
Reply With Quote
     
     
  #92  
Old Posted Jun 29, 2021, 8:35 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,304
Wow, they didn't even save the bricks. This won't be facadism but a replication.
Reply With Quote
     
     
  #93  
Old Posted Jun 29, 2021, 8:47 PM
PhilJones PhilJones is offline
Registered User
 
Join Date: Jun 2021
Location: Ile-de-Hull, Quebec, Canada
Posts: 2
They may have carted off the bricks separately from the other rubble, can't say for certain. Definitely weren't being delicate about it.
Reply With Quote
     
     
  #94  
Old Posted Jun 29, 2021, 9:16 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,428
Quote:
Originally Posted by PhilJones View Post
The demolition of those buildings and construction of the new building are happening right outside my balcony (I'm in Le W/E Phase I). I've been documenting it since the first time I spotted fire fighters hacking at the old apartment building there.
They started blasting today.
Here's an album that I'm keeping updated, including the mockups I found in this thread (thanks!) and some historical context for the site. The destruction of the apartment building was particularly dramatic.
Great pics! Thanks for sharing that album... very well documented. And welcome to the forum!
Reply With Quote
     
     
  #95  
Old Posted Aug 3, 2021, 5:12 AM
Nowhere Nowhere is offline
Registered User
 
Join Date: May 2018
Posts: 228
Excavation is well underway. Anyone knows if they will build both towers at the same time ?
Reply With Quote
     
     
  #96  
Old Posted Aug 3, 2021, 3:23 PM
Harley613's Avatar
Harley613 Harley613 is offline
Registered User
 
Join Date: Jun 2009
Location: Aylmer, QC
Posts: 6,878
The excavation is huge. Is it really just for the short tower in the renderings? Are the 33 story towers happening?
__________________
Instagram: https://www.instagram.com/the.harleydavis/
Reply With Quote
     
     
  #97  
Old Posted Aug 4, 2021, 1:03 AM
Nowhere Nowhere is offline
Registered User
 
Join Date: May 2018
Posts: 228
I didn't realize that this project include a smaller building as well. I'm hoping that they're building at least one of the towers. Multi-phase projects sometimes have the full excavation done for the first phase in prevision of future buildings, so I hope that it's not the case there.
Reply With Quote
     
     
  #98  
Old Posted Sep 26, 2021, 9:16 PM
sgera sgera is offline
Registered User
 
Join Date: Apr 2002
Posts: 205
Quote:
Originally Posted by Nowhere View Post
I didn't realize that this project include a smaller building as well. I'm hoping that they're building at least one of the towers. Multi-phase projects sometimes have the full excavation done for the first phase in prevision of future buildings, so I hope that it's not the case there.
Went by today - excavation pit is massive… at least 5 stories deep and likely setup for multiple building given the size … I would guess this is for larger towers. Would expect crane(s) to be up before winter.
Reply With Quote
     
     
  #99  
Old Posted Sep 26, 2021, 10:54 PM
SL123 SL123 is offline
Registered User
 
Join Date: Mar 2021
Posts: 1,915
Quote:
Originally Posted by sgera View Post
Went by today - excavation pit is massive… at least 5 stories deep and likely setup for multiple building given the size … I would guess this is for larger towers. Would expect crane(s) to be up before winter.
Some of the parking space is probably for the grocery store.
Reply With Quote
     
     
  #100  
Old Posted Oct 20, 2021, 7:17 AM
ponyboycurtis's Avatar
ponyboycurtis ponyboycurtis is offline
Cigritbutt enthusiast
 
Join Date: Apr 2021
Location: Blahttawa
Posts: 1,583


I would guess that this excavation is for the shorter building and one of the towers.



Rue Saint-Redempteur is 2 "houses" to the left of this photo and was seemingly non existent when I took this photo, although I wasn't really looking for it. It seems to part of the staging yard for the moment.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Gatineau
Forum Jump



Forum Jump


All times are GMT. The time now is 6:28 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.