Quote:
Originally Posted by York1
Thanks for the pictures of the Hard Rock. Is there a time table when the city says it has to be finished?
|
Not sure what the City's timeline is, but the Developer's is as follows:
-Demo 1022 Iberville, and 1019-25, 1027 Canal by late May, then remove tower crane that's still suspended over Canal Street
- Recover bodies of workers by early June.
- Remove upper floors of tower by mid-July
-Remove lower floors of tower through Summer and early Fall, fully cleared by October.
More info at:
https://www.nola.com/news/politics/a...f162d9e2c.html