HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates


Reply

 
Thread Tools Display Modes
     
     
  #21  
Old Posted Aug 4, 2022, 7:04 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Have completed the exterior brick work on the north end 3 story podium now.
Reply With Quote
     
     
  #22  
Old Posted Aug 25, 2022, 7:46 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
They have now removed the tower crane from the site. Work continues on the exterior insulation.
Reply With Quote
     
     
  #23  
Old Posted Sep 15, 2022, 3:49 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
The north end has made good progress with exterior brick with the east side now complete up to the 8th floor and the west side up to the 5th floor. Will have to setup scaffolding for the 5 floors of the north face because of the setback 3 story podium. Likely a couple of more months of brick work to go.
Reply With Quote
     
     
  #24  
Old Posted Oct 26, 2022, 7:40 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Have made some progress on exterior brick on the west side south of the large lobby entrance. Only a few more floors to go and they should be able to move the lift swing station around the construction elevator strip and continue around the south end of the building.
Reply With Quote
     
     
  #25  
Old Posted Nov 24, 2022, 5:28 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Nearly done the exterior brick in the middle section of the west wall above the large lobby wing. Should be starting on the south end of the west side next week.
Reply With Quote
     
     
  #26  
Old Posted Dec 2, 2022, 6:25 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Close to finishing the exterior brick work on the west wall on the 3 floor southern end of building.
Reply With Quote
     
     
  #27  
Old Posted Feb 15, 2023, 4:03 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Still working on the exterior brick installation with the west side lobby wing now nearly done with exterior brick and stone. The scaffolding is now setup on the south end east side wall and brick is now up to the 2nd floor level. Still alot of east side wall to complete and the south wall hasn't started as of yet.
Reply With Quote
     
     
  #28  
Old Posted Apr 18, 2023, 6:17 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
They have removed the construction elevator from the west side to finish the exterior brick installation on the west side. Still have the south wall and the east side wall above the connection to original building left to install.
Reply With Quote
     
     
  #29  
Old Posted Jun 5, 2023, 11:11 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Well it took quite a long time but they have finally finished installing the exterior brick on this building. Just some final touch-ups and the masonry contractor can pack up and clean up the site. Should see landscaping crews and grading for parking lot soon as they finish up the interior as well.
Reply With Quote
     
     
  #30  
Old Posted Jul 18, 2023, 1:36 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Small zoning change to allow a "Living classroom" to be setup in the new addition to this site.


PPM is scheduled for PEC on Sept 18th.



https://london.ca/sites/default/file...-%20Z-9640.pdf
Reply With Quote
     
     
  #31  
Old Posted Oct 25, 2023, 4:24 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Landscaping of the former construction staging area is well under way now with topsoil being trucked in.
Reply With Quote
     
     
  #32  
Old Posted Oct 25, 2023, 8:22 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,455
There will be 2 more apartments built on this site, just not sure when.
Reply With Quote
     
     
  #33  
Old Posted Oct 25, 2023, 8:55 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 5,783
Certainly they have the land available. Will they be retirement units or LTC or normal apartments?



Quote:
Originally Posted by GreatTallNorth2 View Post
There will be 2 more apartments built on this site, just not sure when.
Reply With Quote
     
     
  #34  
Old Posted Oct 25, 2023, 9:08 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,455
One will be a 55+ seniors building & the other will be a regular apartment building for anyone.
Reply With Quote
     
     
End
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 11:36 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.