Originally Posted by mrnyc View Post
???

the chart says start is second half of 2021 and completion second half of 2028.

thats seven and a half years.

maybe they are being optimistic and generous.

If you're talking about 15 Penn, that's 2022 to 2028. So my factors of rougtly 2 years of demo and 4 years of construction is correct. BTW, that chart isn't something handwritten in stone. 270 Park started demo in 2019 and will be complete in 2024 (although construction did start before demo is complete). But even factoring in an extra year, that would still only be six.