LA's Crenshaw line is looking very iffy for September and maybe even for 2021. During this week's construction update the project managers expressed increasing frustration with the contractors tasked with completing and testing the electrical and communication equipment in the underground stations. The short story is that they need at least 5 months of testing after that work is complete and they don't think that it will be completed by April. The contractor tasked with testing the equipment has been waiting months for installation to be completed and the contractor that's supposed to complete installation has not committed the necessary resources to complete it.