another pour yesterday. This marks a 13-day cycle between slab pours since the last floor, of which included a long weekend with Labour Day. Things are definitely speeding up, especially if they can maintain a 12-13 day cycle. It's still slower than a lot of projects but is downright lightning speed compared to how this project has typically been moving.