Originally Posted by Pedestrian View Post
I'm not arguing it won't work. Just telling you (and everyone) what I've read about HOW it will work: Trains running at same speed between stations, new sidings (i.e "passing tracks") to allow the HSR to pass stopped CalTrains (presumably at stations where the HSR doesn't stop).
There are 19 intermediate stations at least, the express HSR trains will only stop at one, that leaves 18 others to choose from for that pass to occur. It is possible to set a schedule where they need just one passing siding. Any additional passing sidings just adds flexibility to the scheduling of the trains.
I doubt they will need 19 or more passing sidings, whether they be at stations or between them.