Barton Malow has finally gotten this project on their social media platform, which means we're getting closer to actual construction.



Quote:
Barton Malow Preps for Five-Year Project

By Irwin Rapoport – CEG Correspondent

Wed June 27, 2018 - Midwest Edition #13
Quote:
The project consists of two buildings. To the south will be a 58-story tower building with residential capacity of between 330 and 450 units above 11 floors of amenity and exhibition space. The top floors of the tower will consist of a multi-level public observation deck providing spectacular vistas of the city. At the north is a 10-story “block” building that will house a ground floor market and have five floors of large, flexible space designed to accommodate a wide variety of events, conferences, technology attractions, etc., and four floors of office space at the top. Under both buildings will be two floors of semi-automated underground parking for 700 vehicles.

“The complex is a bit of a homage to Detroit, in terms of the exterior skin,” said Joe Guziewicz, Bedrock's vice president of construction. “It starts out with terracotta at street level and transitions to a more modern glass structure as it goes up the building. It's an interesting play off of what's around it and definitely a nod of the Detroit heritage, which is rich in architectural design with Albert Kahn buildings. Our project is a very modern take on that.”
Quote:
Once the demolition of an existing parking deck is complete, the construction will begin on the tower's foundations and superstructure. As the tower comes out of the ground, the new parking structure will follow. The 10-story building will be the last to emerge and work will continue on both structures concurrently and year-round.

“Building construction in winter is common in Michigan,” said Lorenzo. “Some of the most complex and long-lead systems include structural steel, curtain wall [aluminum/glass enclosure] and vertical transportation [elevators/escalators]. Early design packages will be released to expedite procurement to match the flow of work.”

For the 2018 construction season, the goals are to complete demolition and begin the tower foundations. Most of 2019 will be spent building the structure. The interior work will begin as soon as there is clear floor area to start. Enclosure work is key to completing the final build-out and finishes.

As the construction progresses, the number of workers will increase. At peak, it is expected that there will be up to 600-plus workers on-site.
Lots and lots of detail and good information in this piece, including the fact that we finally get confirmation that the 700-space parking garage will be "semi-automated." An old graphic seems to have shown this, but we get that confirmed, here. We also learn that we're going to have some nice terra cotta near the base.