I was on a CRE webinar with some of the project team today... really incredible stories like you often get in these big historic projects.

-Building is 80% leased up
-Rooftop is substantially complete and will open to the building tenants next week (7/1)
-No public access to the rooftop at first but a restaurant of some kind is planned - yet to start concept phase, probably 2022 opening at the earliest
-Ground-level food court by 16" On Center should be starting build-out this summer, including an outdoor plaza overlooking the river
-No firm plans to build a riverwalk at this time
-Work continues at the track level to reinforce and shore up the concrete structure
-Work on the 290/Congress tunnel should also start this summer

I meant to ask about the plaza areas along Canal, but I forgot... I assume these are on hold until the city rebuilds the Canal St viaduct.