View Single Post
  #2284  
Old Posted Mar 30, 2018, 1:00 PM
k1052 k1052 is offline
Registered User
 
Join Date: Oct 2007
Posts: 2,237
Quote:
Originally Posted by chiphile View Post
That terminal configuration in the latest rendering looks incredible and more in line with modern airport design. Still wish they went all the way west though with two additional concourses. That damn diagonal runway that receives 2% of landings still doesn’t make sense to me as it eliminates half of one of the new concourses.

I count approximately 194 gates in the rendering. Right now ohare has 182 gates. So this isn’t an expansion as much as a realignment of gates. At $8.5 billion, these 12 additional net gates must be the most expensive in history at $700 million each. Even if the rendering is a conservative estimation of gates, the total number likely won’t exceed 200-210. A welcome update to the terminal complex nevertheless. Maybe with full build out we see 85 to 90 million pax per year.
The two remaining diagonals will still be needed for certain wind conditions that exceed crosswind limits, although that's expected to be a very small percentage of time.

It's more gates than that, should meet the 220 figure when this phase is done. Don't take the renderings too literally. They show a ton of 4 engine aircraft too...
Reply With Quote