^12 floors in 10 weeks would be considered a 4-day pour cycle as you only count workdays. They may have even shifted to a 3-day cycle now that the floors look typical. With the flying formwork system they are using, a 3-day pour cycle would be the best that is economically achievable. In NYC they do 2-day pour cycles but they come back and top the slabs with a finish topping after the structure is up because the finish is so poor when you go that quickly.
|