View Single Post
  #1067  
Old Posted Oct 31, 2018, 10:12 AM
Bombardier Bombardier is offline
Registered User
 
Join Date: Aug 2016
Location: Chicago, IL
Posts: 467
^12 floors in 10 weeks would be considered a 4-day pour cycle as you only count workdays. They may have even shifted to a 3-day cycle now that the floors look typical. With the flying formwork system they are using, a 3-day pour cycle would be the best that is economically achievable. In NYC they do 2-day pour cycles but they come back and top the slabs with a finish topping after the structure is up because the finish is so poor when you go that quickly.