Chicago CREATE Lands $19.2 INFRA grant

CREATE Project GS9 Archer Avenue /Belt Railway grade separation

USDOT Selection
Project Description
The Illinois Department of Transportation will be awarded $19,137,780 to grade separate Archer Avenue
roadway and two existing Belt Railway of Chicago (BRC) rail tracks. The project will reconstruct Archer Avenue
and lower it approximately 15 feet under a new rail bridge to serve the existing BRC tracks, add elevated
pedestrian and bicycle sidewalks under the rail bridge with lighting, relocate utilities, and install a combined
storm and sanitary sewer along Archer Ave with rehabilitated combined sewers adjacent to the project site