Posted Jun 19, 2020, 5:41 AM
|
heavy user of walkability
|
|
Join Date: May 2008
Location: Mission Bay, San Francisco
Posts: 3,150
|
|
in the June 2020 Potrero View (which I don't see online yet), there were two things of note:
- the aim is that Crane Cove Park will open this fall, though it will still be a work in progress on some fronts:
- 19th St will apparently still be under construction
- a few items have been deferred until more money can be raised, since bids for the overall work came in higher than expected:
- the crane tops, which may return as early as 2022
- a dog run
- a children's play area
- the start date for construction of the public school on block 14 has been pushed back about a year, to spring 2023, with completion slated for 2025
|