Transit center developments...
http://www.lowermanhattan.info/const...ion_34922.aspx
*The following information was last updated on January 8, 2010.
-Excavation and site preparation in east bathtub. Constrolled blasting for excavation will take place from January 11 through March 2010.
-Excavation and bracing at the concourse under West Street.
-Excavating beneath and installing steel below the 1 subway box
-Long-lead procurements of elevator, escalator, and electrical equipment
-Future restored Fulton Street substructure and decking is underway inside WTC site, including concrete pours
-Construction of the West Street pedestrian underpass (the "east-west connector") -- to link the WTC with Battery Park City's World Financial Center -- is active on the west side of the WTC site just south of the Freedom Tower and across West Street. Installation of 47 pre-cast arches ended in August 2008; roof structure now being installed.
-East-west connector structural components are being installed across West Street
-Headhouse construction is active outside the WFC's Winter Garden with coordination with Brookfield Properties