View Single Post
  #51  
Old Posted Sep 29, 2023, 3:09 PM
one_brick_at_a_time's Avatar
one_brick_at_a_time one_brick_at_a_time is offline
Registered User
 
Join Date: Apr 2009
Location: Regina/Toronto
Posts: 2,246
An update on the current progress of the Prince Edward Building. (Sept. 29th/2023)

The Globe Theatre Revitalization is progressing into a new phase of the construction work. Major structural upgrades to the building are nearly complete after demolition revealed significant degradation of nearly every structural element in the building. Stairs, walls, beams, and floors were, in many cases, supported by little more that paint, grout, and the hopes of previous generations.

The dramatic mainstage volume, now extending from the main floor trap room up through the original roof four stories above, has taken shape. The true “in-the-round” theatre form has been revealed as the three floors of scaffolding below the now complete and state-of-the-art catwalk system has been removed. The seating bowl form can be clearly seen, and trades are now installing mechanical and electrical distribution systems as steel stud framing is installed. The roof, itself a significant project, is complete, and the massive air handling system serving the theatre is in place.

The service elevator has been installed in the back-of-house space and will be used to move material up and down in the building during construction. Basement mechanical and electrical rooms are full of equipment and steel stud framing is ongoing throughout the building.
The challenges have not ended with the (near) conclusion of the structural patching. Water was found to be seeping into the main passenger elevator pits. Testing has revealed that it is not storm or potable water, indicating that a leak from a city or adjacent building sewer line is the likely culprit. Investigation and mitigation is underway. The Scarth Street entrance discussions have been ongoing with the City of Regina, and your team has advocated for the inclusion of this necessity for the Globe and amenity for the City’s public realm.

Schedule has been a challenge for the Construction Management (CM) team as the building condition continues to prevent momentum on the project. Difficult decisions made to mitigate costs months or years ago have resulted in delays due to the unpredictable nature of the building state. The available budget has been eroded as million of dollars in additional structural components have been added to ensure the long-term viability of the building. As a result, restoration of the exterior masonry and copper awaits additional federal funding.

The importance of the Globe Theatre as a cultural hub and heritage landmark in the heart of the city drives your team to make the project a success.

James Youck
Architect, P3A




Last edited by one_brick_at_a_time; Sep 29, 2023 at 4:37 PM.
Reply With Quote