Quote:
Originally Posted by ASU Diablo
What's a reasonable estimated date as to when McKinley Green may break ground based on this latest update?
|
1st Review is running about 60 days for building permits, 2-4 weeks of revisions, 2nd Review is about 30 days, so I would safely say about 4 months till permit. That doesn't mean they don't start rough grading, and utility work prior, but I would say sometime in July for full building permit release.