CTA Begins Plan To Rebuild Red Line’s Sheridan, Rogers Park Stops In Massive North Branch Overhaul
Block Club Chicago | Joe Ward | 9:20 PM CDT on Mar 16, 2023

Quote:
As work continues on the rebuilding of the Red Line in Uptown and Edgewater, the CTA is now turning its attention to reconstructing the remainder of the transit line’s north branch.

The CTA is in the early stages of planning to rebuild the century-old Red Line stations and rail infrastructure not yet included in the massive Red-Purple Modernization Project.

That includes rebuilding the Sheridan stop and overhauling much of the Red Line infrastructure in Rogers Park, possibly including the Howard Street terminal, CTA officials said at a community meeting Tuesday.

CTA is also planning to overhaul the Purple Line branch that extends into Evanston and Wilmette, officials said.
Quote:
The Sheridan station, near the corner of Sheridan and Irving Park roads, is sandwiched between buildings. Its current footprint is too small for fully accessible features.

The station needs to be fully reconstructed to make it accessible, but engineers and architects will have to get creative if they are to work within the existing station footprint, said Christina Bader, project manager at CTA.

The Red Line tracks follow an S-curve just north of Sheridan, a feature that slows down service. Straightening it out will be a challenge as CTA only owns the land within the existing rail infrastructure, Bader said.

“There’s both old and new development that makes streaming the curve challenging,” Bader said at a community meeting Tuesday. “We’re looking at all options here, which include station location.”