IAH Redevelopment / Terminal B

https://www.houstontx.gov/council/co...evelopment.pdf

Summarized by Houston19514 on HAIF

Quote:
United's plans for Bush Intercontinental Terminal B are being presented today.

Huge rebuild of Terminal B. They will demolish the original banjo flight stations and build two new concourses to serve narrow body and wide body aircraft. Look like about 22 gates total, including 4 wide body gates.

Will double the footprint of the central processor; new inbound and outbound baggage systems, new security screening checkpoint, new ticketing lobby. They will take the land that is currently surface parking east of the existing central processor.

B South will be renovated to allow for 18 gates for large regional jets, with passenger loading bridges at each gate.

They expect to start enabling projects early in the third quarter. Construction on the B North concourses to start mid-4th Quarter (2023). Also work on the new Processor building will start on the surface lot mid-4th Quarter (2023). B South work is to start early next year. B South to be completed mid-year 2025. North concourses and processor work to be completed mid-year 2026.