As recently as a couple of weeks ago that page said:
Quote:
Ground-up mixed-use development located on the site immediately east of the Tribune Tower currently a parking lot. Final scale of project TBD. The project is currently going through entitlements with Tribune West (the two projects are part of the same Planned Development).
Est. Construction Start Date: Mar-2023
Est. Construction End Date: Oct-2026
|
http://web.archive.org/web/202302140...front-plaza-dr
vs what it says now:
Quote:
Fully-entitled development site adjacent to existing Tribune Tower Residences. Entitlement allows for approximately 1.3M square feet and a height of 1442 feet. The site is allowed up to 564 units (125 condos/439 rentals) 250 hotel keys and 426 parking spaces.
Est. Construction Start:
February - 2024
Est. Construction End:
September - 2027
|
https://www.cimgroup.com/bidding-opportunities
So that is indeed a promising update...