City Gardens Update



April 2022



October 2022 - Glad I got down there when I did to see both footings poured and some sitting empty. They look around 4 feet thick. Pretty cool to see an entire city block excavated down that much. Says it will be a 3 level parkade.




Crane being installed this week. Looks to be going in the center of the site so my guess is just 1 will be going up.