Quote:
Originally Posted by ardecila View Post
Western access requires an underground people mover, but based on the phasing of new terminals I don't think they will add a people mover until the 2nd satellite terminal opens, which might not be until the mid 2030s.

T2 is landside and the 1st satellite will be directly connected to T1's remote concourse. You don't really need the people mover until the 2nd satellite comes online. At that point I imagine they would just continue digging the tunnel to the west and build a small, temporary check-in facility (pickup/dropoffs only, no checked bags). Basically just a few electronic kiosks for each airline and then a security screening.
From what I remembered. The timeline was this:

Terminal 5 Expansion:
Break ground 2019
Completed in 2021

Sattelite Concourses for Global Terminal:
Break ground 2022
Completed in 2024

Demolish Existing Terminal 2

Global Terminal
Break ground 2024
Completed in 2028

Then again, these dates could easily be delayed with the pandemic.