harryc Apr 16, 2020 4:20 PM

Quote:

Originally Posted by SteelMonkey (Post 8895335)
Is this project abnormally slow for some reason Im unaware of? The comparable tower on Wacker started drilling on May 30th and pouring the mat on Aug 17th 2019. They started drilling here on Dec 28th and arent that close on April 15th.

Seems more like an archaeological dig than tower construction.

From looking at the work - it is the archelogical aspect ;-) That 12'+ trench around the South and East perimeter is criss-crossed by more than one utility run, the nasty liquid filled ones - most likely in vintage cast iron.

Last I checked they were making good progress on excavating out the area for the mat, note 110 N Wacker did little to no excavation.

SteelMonkey Apr 16, 2020 4:37 PM

Quote:

Originally Posted by harryc (Post 8895349)
From looking at the work - it is the archelogical aspect ;-) That 12'+ trench around the South and East perimeter is criss-crossed by more than one utility run, the nasty liquid filled ones - most likely in vintage cast iron.

Last I checked they were making good progress on excavating out the area for the mat, note 110 N Wacker did little to no excavation.


Understood and that makes sense. Thanks for the info

Downtowntransplant Apr 16, 2020 5:24 PM

3-4 months is not slow at all, especially considering how large this project is.

The Lurker Apr 16, 2020 6:52 PM

Quote:

Originally Posted by SteelMonkey (Post 8895335)
Is this project abnormally slow for some reason Im unaware of? The comparable tower on Wacker started drilling on May 30th and pouring the mat on Aug 17th 2018. They started drilling here on Dec 28th and arent that close on April 15th.

Seems more like an archaeological dig than tower construction.

Global pandemic? Sure work is still commencing but I have to assume they're working with a limited crew at the very least.

harryc Apr 20, 2020 8:24 PM

April 19

Chicago | BMO Tower by Harry Carmichael, on Flickr

Chicago | BMO Tower by Harry Carmichael, on Flickr

marothisu Apr 25, 2020 4:50 PM

Full building permit was issued yesterday

CrazyCres May 2, 2020 2:02 AM

Chicago plan commission presentation!

https://www.chicago.gov/content/dam/...20_s_canal.pdf

chicubs111 May 2, 2020 2:46 AM

^its a bit too squat for a 1.5 million sq foot building..they need to stretch out those setback a bit more...should be closer to 800ft you would think atleast

harryc May 2, 2020 3:23 PM

May 1

Chicago | BMO Tower by Harry Carmichael, on Flickr

Assembling the climbing form walls
Chicago | BMO Tower by Harry Carmichael, on Flickr

Chicago | BMO Tower by Harry Carmichael, on Flickr


Ready for the (a ?) mat
Chicago | BMO Tower by Harry Carmichael, on Flickr

Chicago | BMO Tower by Harry Carmichael, on Flickr

Nubs for tieing into the mat - not extender/couplers like at One Chicago.
Chicago | BMO Tower by Harry Carmichael, on Flickr


Chicago | BMO Tower by Harry Carmichael, on Flickr

harryc May 10, 2020 7:36 PM

May 7









rivernorthlurker May 18, 2020 6:07 PM

Le Flood.

via https://app.oxblue.com/open/clarkcon...erconstruction

05.16.2020

https://i.imgur.com/342RRYG.png

05.18.2020

https://i.imgur.com/yWZu8I3.png

r18tdi May 18, 2020 9:20 PM

Quote:

Originally Posted by chicubs111 (Post 8910395)
^its a bit too squat for a 1.5 million sq foot building..they need to stretch out those setback a bit more...should be closer to 800ft you would think atleast

Perhaps. I'm more disappointed by the blank wall at street-level along Clinton.

harryc May 25, 2020 11:11 AM

May 20












KWillChicago May 26, 2020 10:23 PM

From the webcam looks like the crane is going through the middle of the building. I imagine the mat pour in about two weeks?

CrazyCres May 26, 2020 10:30 PM

More like next week for a mat pour

builder8 May 27, 2020 11:45 AM

Mat Pour starts this morning.

RedCorsair87 May 27, 2020 2:12 PM

^Well that escalated quickly.

BVictor1 May 27, 2020 6:34 PM

Quote:

Originally Posted by builder8 (Post 8933717)
Mat Pour starts this morning.

Mat pour happening now. Not very big. Construction guy told me about 2,100 cu yd.

BVictor1 May 28, 2020 12:32 AM

05/27/2020

https://uniim1.shutterfly.com/ng/ser...625832/enhance

https://uniim1.shutterfly.com/ng/ser...625838/enhance

https://uniim1.shutterfly.com/ng/ser...625829/enhance

rivernorthlurker May 28, 2020 1:44 AM

Quote:

Originally Posted by BVictor1 (Post 8934529)
05/27/2020

Donesies.

via https://app.oxblue.com/open/clarkcon...erconstruction

https://i.imgur.com/RL632CS.png