Updates on the downtown projects
Wells Fargo Towers: Nearly complete, both are T/O
4Marq: Completed, open for moving
Lat45: Completed, many people have moved in so far
Edition Apartments: All 3 are T/O, work has begun on the exterior
Raddison Red: Last I saw, the base is still being formed
Portland Tower: Currently working on the 6th structural floor. 26 units have been sold, or 23%.
AC Hotel: Just one more floor until it's T/O!
Plymouth Hotel: Windows are being replaced each week. It's hard to tell from the street level what is happening
The Encore: Finally rising above the ground. 2 stories above grade so far
100 Hennepin: Trees have been taken down, parking lot is closed!
T3: Elevator shafts are being worked on now. This one is going pretty slowly
Be The Match North Loop: Employees have moved in
Arctic Cat HQ: The 2 additional floors have been added, a lot of new windows
602 Apartments: Above 3 stories last I checked
Mill City Quarter: Nearly T/O! They're using pre-fab here. It's interesting.
That's all I can think of right now.. I'll post some renderings now of projects you guys may have missed.