  #1681  
Old Posted Jan 20, 2015, 6:16 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Here is a bit more info on the planned High Performance Computing Center tower.

C&W RELEASES RFQ FOR 600K SF GA TECH TOWER

Quote:
Cushman & Wakefield released an RFQ seeking developers to help Tech expand Technology Square and develop the High Performance Computing Center. The mixed-use tower will include in excess of 600k SF of office space, half of which will be leased by Georgia Tech, and another 100k SF that is under LOI with an unidentified tech company, according to RFQ documents here.

“Details of these industry partners and their level of commitment will be disclosed to the finalists during the advanced stages of the RFP phase,” officials state in documents.
Reply With Quote
     
     
  #1682  
Old Posted Jan 20, 2015, 6:52 PM
Atlanta3000 Atlanta3000 is offline
BANNED
 
Join Date: Nov 2013
Location: Buckhead
Posts: 2,763
Quote:
Originally Posted by smArTaLlone View Post
Here is a bit more info on the planned High Performance Computing Center tower.

C&W RELEASES RFQ FOR 600K SF GA TECH TOWER
I just glanced through the RFQ. Can we assume this will not start construction this year? Also, will the winning developer be proposing their own design or is that something GA Tech is providing?
Reply With Quote
     
     
  #1683  
Old Posted Jan 20, 2015, 10:27 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Quote:
Originally Posted by Atlanta3000 View Post
I just glanced through the RFQ. Can we assume this will not start construction this year? Also, will the winning developer be proposing their own design or is that something GA Tech is providing?
In earlier documents, Tech did indicate the intention to begin construction in 2015. At this point however, its appears unlikely to start this year. The RFQ/RFP process may take several months and then the project will have to go through permitting.

The developers that qualify may add some unique elements to Tech's requirements but I think the basic parameters of the project have been set by GT.

Last edited by smArTaLlone; Jan 21, 2015 at 7:21 AM.
Reply With Quote
     
     
  #1684  
Old Posted Jan 20, 2015, 10:59 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Georgia World Congress Center seeks developer for convention hotel

http://www.bizjournals.com/atlanta/r...loper-for.html

Quote:
The Georgia World Congress Center Authority released a request for qualifications that could lead to a 1,200-room convention hotel in downtown Atlanta.
The Authority is seeking responses from developers specializing in large urban hotels from 800 to 1,200 rooms on the campus of the Georgia World Congress Center.
Responses are due Feb. 16.
Reply With Quote
     
     
  #1685  
Old Posted Jan 21, 2015, 5:53 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
The creatively named "Atlantic House" tower set to break ground

http://www.atlantaintownpaper.com/20...lizzie-chapel/

Quote:
A groundbreaking ceremony is set for Jan. 30 for the latest project by Novare Group called Atlantic House. Located at 1163 West Peachtree Street in Midtown, the 32-story tower will feature 400 apartments and 11,500 square feet of retail space on the ground floor.

Last edited by smArTaLlone; Jan 21, 2015 at 5:54 PM. Reason: The creatively name "Atlantic House" set to break ground
Reply With Quote
     
     
  #1686  
Old Posted Jan 23, 2015, 9:55 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Alta at the Park to be condos and could break ground this summer

http://www.bizjournals.com/atlanta/p...the-condo.html

Quote:
The first high-rise condo tower in more than five years could break ground this summer in Atlanta, another strong indication demand is returning for new intown units.

Atlanta-based Wood Partners LLC is considering a 198-unit project overlooking Midtown's Piedmont Park.

"We are building condo product," Wood Partners' Bennett Sands told a group of Midtown residents during a Jan. 20 presentation of the mixed-use project called Alta on the Park.

Last edited by smArTaLlone; Jan 24, 2015 at 7:26 PM.
Reply With Quote
     
     
  #1687  
Old Posted Jan 25, 2015, 12:32 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Middle Midtown

This picture reminded me of the article a few weeks ago about 7 towers that are in various stages of development in and around Tech Square south of 10th Street. This picture illustrates how the mid section of Midtown is really beginning to fill in (assuming most of these projects get built), with those 7 towers and a few other developments in the area.
  1. Square on 5th
  2. University House
  3. Modera Midtown
  4. NCR Headquarters
  5. Georgia Tech HPCC
  6. 33 Peachtree Place
  7. 880 West Peachtree
  8. 782 Peacthree
  9. Seventh Midtown
  10. Eviva Peachtree
  11. Broadstone Terraces

Reply With Quote
     
     
  #1688  
Old Posted Jan 25, 2015, 3:46 PM
RocketSurgeon RocketSurgeon is offline
Registered User
 
Join Date: Feb 2014
Location: Atlanta
Posts: 945
The last cycle (Atlantic Station, Midtown Mile, etc.) produced a lot of infill in a few spots, but it was kind of a false start... I think this one is proving to be transformative. It will give Midtown a real sense of place and make the blight much less apparent, which will boost demand even more. I think we're finally hitting critical mass.
Reply With Quote
     
     
  #1689  
Old Posted Jan 27, 2015, 2:47 AM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Cyan on Peachtree nearing completion.

Reply With Quote
     
     
  #1690  
Old Posted Jan 28, 2015, 4:59 PM
shivtim's Avatar
shivtim shivtim is offline
Registered User
 
Join Date: Aug 2008
Location: Midtown Atlanta
Posts: 2,360
I don't think I'd seen this figure of MARTA's proposed Avondale Estates TOD. I'm sure it's probably just a massing/design mock-up, but it would be great if they actually build something like this.

Reply With Quote
     
     
  #1691  
Old Posted Jan 28, 2015, 11:22 PM
joecool's Avatar
joecool joecool is offline
Ahhhh KELLY CLARKSON!!!
 
Join Date: Dec 2002
Location: Atlanta
Posts: 779
Quote:
Originally Posted by smArTaLlone View Post
Here is a bit more info on the planned High Performance Computing Center tower.

C&W RELEASES RFQ FOR 600K SF GA TECH TOWER
I thought that was the old rendering. I like the newer one better.
__________________
What doesn't kill you makes you stronger!!!
Reply With Quote
     
     
  #1692  
Old Posted Jan 30, 2015, 6:39 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Midtown and Tech Square on a Roll

Germany's RIB Software to relocate North American HQ to Midtown's Tech Square


Quote:
RIB Software AG will relocate its North American headquarters to a proposed 700,000-square-foot mixed-use tower in Midtown's Technology Square.
Stuttgart, Germany-based RIB develops project management software for the construction industry, including project conception, planning, and budgeting. RIB, which employs about 700 and trades on the Frankfurt Stock Exchange, has an Atlanta office in Northpark Town Center.
Reply With Quote
     
     
  #1693  
Old Posted Jan 31, 2015, 4:38 AM
Libertarian's Avatar
Libertarian Libertarian is offline
Registered User
 
Join Date: Feb 2013
Posts: 1,430
I understand RIB has formed a strategic alliance with Tech, but where besides the Atlanta Business Chronicle is this North American relocation being reported? I hope it is indeed correct but would like to see some confirmation.
Reply With Quote
     
     
  #1694  
Old Posted Feb 1, 2015, 5:52 AM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Skyhouse Buckhead set to open in March
Reply With Quote
     
     
  #1695  
Old Posted Feb 2, 2015, 8:00 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Amli at Cityplace development Takes Shape

Reply With Quote
     
     
  #1696  
Old Posted Feb 3, 2015, 3:22 AM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Heights at West Midtown

Reply With Quote
     
     
  #1697  
Old Posted Feb 6, 2015, 2:56 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
First look at Scott Smith’s big plan for Underground Atlanta

http://www.bizjournals.com/atlanta/p...derground.html

Quote:
The prospective buyer of Underground Atlanta envisions developing about 1,000 new residential units as part of his firm's redevelopment plans — including a new high-rise residential tower on Peachtree Street.

T. Scott Smith, CEO of WRS Inc., which has a contract to buy the 12 acres from the city of Atlanta for $25.75 million, has submitted the preliminary site plan of the project to the city. Smith said when completed, WRS and its development partners will invest between $150 million to $200 million to redevelop Underground.
Reply With Quote
     
     
  #1698  
Old Posted Feb 6, 2015, 5:14 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Yoo on the Park finally moving forward?

Kaseem Reed's calender includes this item...

"Yoo On The Park Groundbreaking" as an upcoming event on Juniper Street, scheduled for 11 a.m. on Feb. 18.

http://atlanta.curbed.com/archives/2...-come-soon.php
Reply With Quote
     
     
  #1699  
Old Posted Feb 9, 2015, 5:13 PM
smArTaLlone smArTaLlone is offline
Registered User
 
Join Date: Feb 2005
Posts: 8,584
Will 2015 be the busiest year of construction Ever in Midtown?

Its starting to look like it could be.

  • Square on 5th : Under Construction
  • University House : Under Construction
  • 60 11th Street : Under Construction
  • 33 Peachtree Place : Under Construction
  • 782 Peachtree : Under Construction
  • Seventh Midtown : Under Construction
  • One Museum Place : Under Construction

  • Atlantic House : Q1 Construction start
  • Yoo on the Park : Groundbreaking Feb 18
  • Amli Arts Center : Filed permits 12/09/2014 ... Possible Construction - March
  • Post Millenium : Filed permits 1/12/2015 ... Possible Construction - April
  • Modera Midtown : Filed permits 1/22/2015 ... Possible Construction - April
  • Broadstone Terraces : Filed permits 1/29/2015 ... Possible Construction - May
  • 1010 West Peachtree : Filed permits 1/30/2015... Possible Construction - May
  • Alta at the Park : Possible Construction - Summer

It seems to typically take about 3 months to get land disturbance permits to start construction so I projected the earliest some of these projects could break ground.

On the down side Eviva Peachtree seems to have stalled in permitting since they first filed some permits back in April of last year. Does anyone have an idea what the issue could be?

Last edited by smArTaLlone; Feb 9, 2015 at 6:17 PM.
Reply With Quote
     
     
  #1700  
Old Posted Feb 9, 2015, 6:04 PM
jpk1292000 jpk1292000 is online now
Registered User
 
Join Date: Mar 2006
Location: Atlanta
Posts: 1,030
Quote:
Originally Posted by smArTaLlone View Post
Its starting to look like it could be.

  • Square on 5th : Under Construction
  • University House : Under Construction
  • 60 11th Street : Under Construction
  • 33 Peachtree Place : Under Construction
  • 782 Peachtree : Under Construction
  • Seventh Midtown : Under Construction
  • One Museum Place : Under Construction

  • Atlantic House : Q1 Construction start
  • Amli Arts Center : Filed permits 12/09/2014 - Possible Construction - March
  • Post Millenium : Filed permits 1/12/2015 - Possible Construction - April
  • Modera Midtown : Filed permits 1/22/2015 - Possible Construction - April
  • Broadstone Terraces : Filed permits 1/29/2015 - Possible Construction - May
  • 1010 West Peachtree : Filed permits 1/30/2015 - Possible Construction - May

It seems to typically take about 3 months to get land disturbance permits to start construction so I projected the earliest some of these projects could break ground.

On the down side Eviva Peachtree seems to have stalled in permitting since they first filed some permits back in April of last year. Does anyone have an idea what the issue could be?
When I drove by this morning, it looked like they were moving dirt at Modera, but I'm not sure...
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > United States > Southeast > Atlanta
Forum Jump



Forum Jump


All times are GMT. The time now is 1:11 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.