  #2041  
Old Posted Jun 20, 2023, 1:27 PM
360_Ray 360_Ray is offline
Registered User
 
Join Date: Apr 2022
Location: Austin
Posts: 145
P11

- Ramps to P11 poured last week. NE corner poured yesterday. Working on west side rebar now.
- 3rd street still blocked off for what I think may be the electrical interconnect work
- Construction elevators now operational up to P6



Reply With Quote
     
     
  #2042  
Old Posted Jun 24, 2023, 10:33 PM
KevinFromTexas's Avatar
KevinFromTexas KevinFromTexas is offline
Meh
 
Join Date: Jul 2001
Location: Austin <------------> Birmingham?
Posts: 57,327
__________________
Conform or be cast out.
Reply With Quote
     
     
  #2043  
Old Posted Jun 25, 2023, 5:49 AM
clubtokyo's Avatar
clubtokyo clubtokyo is online now
クラブトクヨ
 
Join Date: Jul 2013
Location: Austin, TX
Posts: 2,100
Wow that’s beautiful! Kind of reminds me of the edge in NYC.
__________________
Let’s keep building up Austin! #letsgetdense

Last edited by clubtokyo; Jun 26, 2023 at 1:27 AM.
Reply With Quote
     
     
  #2044  
Old Posted Jul 7, 2023, 12:43 AM
corvairkeith's Avatar
corvairkeith corvairkeith is offline
Registered User
 
Join Date: Oct 2008
Location: Austin, Texas
Posts: 1,476


Reply With Quote
     
     
  #2045  
Old Posted Jul 7, 2023, 1:09 AM
We vs us We vs us is offline
Registered User
 
Join Date: Sep 2015
Location: Austin, TX
Posts: 3,588
That's like 8 surface parking lots stacked on top of one another.
Reply With Quote
     
     
  #2046  
Old Posted Jul 8, 2023, 5:55 PM
360_Ray 360_Ray is offline
Registered User
 
Join Date: Apr 2022
Location: Austin
Posts: 145
7/8/23 - Emergency Generator Lift - P12

They are currently working on P12 level up top. Ramps up to the level poured on July 3rd and the NE corner of the level poured this morning.

Meanwhile on the south side they lifted the emergency power generator up to the mechanical area that is on the 3rd street extension space between P3-P6. They brought in a temporary crane because the lift was 47,000 pounds and was too heavy for the tower cranes.

Reply With Quote
     
     
  #2047  
Old Posted Jul 8, 2023, 7:04 PM
SproutingTowers's Avatar
SproutingTowers SproutingTowers is online now
Registered User
 
Join Date: Feb 2020
Location: Austin TX
Posts: 362
Surprised the scaffolding can support that weight.
Reply With Quote
     
     
  #2048  
Old Posted Jul 8, 2023, 8:18 PM
360_Ray 360_Ray is offline
Registered User
 
Join Date: Apr 2022
Location: Austin
Posts: 145
Quote:
Originally Posted by SproutingTowers View Post
Surprised the scaffolding can support that weight.
They never had the full weight on the scaffolding. They turned it 90 degrees with the crane and had half of it on the building P3 ledge and half on the scaffolding while they placed it on skates to then maneuver it into position.
Reply With Quote
     
     
  #2049  
Old Posted Jul 17, 2023, 4:51 PM
360_Ray 360_Ray is offline
Registered User
 
Join Date: Apr 2022
Location: Austin
Posts: 145
P12 Pours Complete

They poured the western side on the 13th and the SE corner this morning. (20 days between the last level).

Added some more ironwork for canopy around the front entrance.

Reply With Quote
     
     
  #2050  
Old Posted Jul 19, 2023, 12:18 AM
360_Ray 360_Ray is offline
Registered User
 
Join Date: Apr 2022
Location: Austin
Posts: 145
Glass Installed 7/18/23

First significant glass skin installed on the P3 level of the NW corner today.

Reply With Quote
     
     
  #2051  
Old Posted Jul 19, 2023, 12:32 AM
clubtokyo's Avatar
clubtokyo clubtokyo is online now
クラブトクヨ
 
Join Date: Jul 2013
Location: Austin, TX
Posts: 2,100
Yay for glass!!
__________________
Let’s keep building up Austin! #letsgetdense
Reply With Quote
     
     
  #2052  
Old Posted Jul 21, 2023, 2:45 PM
360_Ray 360_Ray is offline
Registered User
 
Join Date: Apr 2022
Location: Austin
Posts: 145
Ironwork on 3rd Street

2nd level of ironwork being installed on the southern side between P6 and P8

Reply With Quote
     
     
  #2053  
Old Posted Jul 22, 2023, 1:18 PM
Urbannizer's Avatar
Urbannizer Urbannizer is offline
Moderator
 
Join Date: Jan 2009
Location: 360, St. Edwards
Posts: 12,383
__________________
HAIF
Reply With Quote
     
     
  #2054  
Old Posted Jul 25, 2023, 3:57 PM
randalls randalls is offline
randalls
 
Join Date: Jul 2022
Location: Austin, Texas
Posts: 196
View of Republic construction taken from 300 Colorado.


Reply With Quote
     
     
  #2055  
Old Posted Aug 6, 2023, 5:11 PM
360_Ray 360_Ray is offline
Registered User
 
Join Date: Apr 2022
Location: Austin
Posts: 145
P13 Pours Complete

- They finished pouring P13 on Thursday. Building ramps to P14 now. I believe we have 4 more full levels of parking (14-17), then what looks like a half level, then the amenity level (19). So 6 more floors before we get to the tower portion. At 18 days per level plus I'm guessing maybe an extra month since the last couple levels will be unique that puts us just before the end of the year. With holidays I think we'll probably start the tower around the New Year.

- More ironwork on level 1 as they are installing what look to be the retail area doorways and window framing on the SE and SW corners.

- A little bit more glass and they started installing the skin framework on P5/6 on the SW corner.



Reply With Quote
     
     
  #2056  
Old Posted Aug 6, 2023, 8:16 PM
bobbywest87 bobbywest87 is offline
Registered User
 
Join Date: Apr 2022
Posts: 521
Thanks for the update 360! This thing is absolutely massive!
Reply With Quote
     
     
  #2057  
Old Posted Aug 21, 2023, 9:57 PM
corvairkeith's Avatar
corvairkeith corvairkeith is offline
Registered User
 
Join Date: Oct 2008
Location: Austin, Texas
Posts: 1,476








Reply With Quote
     
     
  #2058  
Old Posted Aug 24, 2023, 8:51 PM
gillynova's Avatar
gillynova gillynova is offline
Registered User
 
Join Date: Mar 2017
Location: Austin / Bay Area
Posts: 2,166
Reply With Quote
     
     
  #2059  
Old Posted Aug 29, 2023, 4:31 PM
gillynova's Avatar
gillynova gillynova is offline
Registered User
 
Join Date: Mar 2017
Location: Austin / Bay Area
Posts: 2,166


Reply With Quote
     
     
  #2060  
Old Posted Aug 30, 2023, 6:58 PM
360_Ray 360_Ray is offline
Registered User
 
Join Date: Apr 2022
Location: Austin
Posts: 145
End of Aug Update

- Concrete - They poured the NE corner of P15 this morning. We have this level and two more full levels of parking to go then a transition level before we get to the amenity deck.
- Glass - They have two levels of glass on most all the building (P3/4) including the first lighted section in the pic below. P5 glass done on West side and working on South side now. P6 glass started in NW corner.
- 3rd street still blocked off as they continue what I think is chilled water interconnect in the street

Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > United States > Texas & Southcentral > Austin
Forum Jump



Forum Jump


All times are GMT. The time now is 4:31 AM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.