- They finished pouring P13 on Thursday. Building ramps to P14 now. I believe we have 4 more full levels of parking (14-17), then what looks like a half level, then the amenity level (19). So 6 more floors before we get to the tower portion. At 18 days per level plus I'm guessing maybe an extra month since the last couple levels will be unique that puts us just before the end of the year. With holidays I think we'll probably start the tower around the New Year.
- More ironwork on level 1 as they are installing what look to be the retail area doorways and window framing on the SE and SW corners.
- A little bit more glass and they started installing the skin framework on P5/6 on the SW corner.