HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Discussion Forums > Transportation


Reply

 
Thread Tools Display Modes
     
     
  #1101  
Old Posted Jul 17, 2015, 12:27 PM
anday anday is offline
Registered User
 
Join Date: May 2015
Posts: 35
Purple Line design and construction could begin May 16, state says

http://www.washingtonpost.com/blogs/...-says/?hpid=z4

"Maryland transportation officials plan to choose a winning bid to design, build and operate a light-rail Purple Line by Jan. 15, and bidders should assume design and construction work could begin May 16, according to new bid solicitation documents released this week."

"The dates included in a revised 2,075-page “request for proposals” sent to bidders Wednesday provides the most detailed project schedule since Maryland Gov. Larry Hogan (R) announced June 25 that the state would build the 16-mile light-rail line if the state paid less, Montgomery and Prince George’s counties paid more, and the overall project was less costly."
Reply With Quote
     
     
  #1102  
Old Posted Aug 6, 2015, 3:35 AM
cambron J's Avatar
cambron J cambron J is offline
Registered User
 
Join Date: Jul 2012
Posts: 150
WMATA: Dulles Corridor Metrorail Project progress update e-mail 08 05 2015

Design Changes Enhancing Safety and Reliability, Cause Phase 2 Delays

More than 150 modifications to the design for Phase 2 as well as weather and construction delays have added about 13 months to the estimated construction period for Phase 2 of the Silver Line. Many of those changes reflect design changes that were made in the final months of construction of Phase 1 and are now being integrated in the Phase 2 design. These changes will enhance safety and reliability.

"Over 100 design changes require additional design, engineering, construction, management and oversight work," said Charles Stark, executive director of the Silver Line project. "The added costs remain within the Phase 2 contingency budget of $550 million and will have no effect on the toll rates on the Dulles Toll Road," Stark said in late April.
Excavation for Phase 2 Stations, Substations To Remove Thousands of Cubic Yards of Dirt and Rock

Excavation for Phase 2 Stations, Substations To Remove Thousands of Cubic Yards of Dirt and Rock


Photo Capital Rail Constructors

The Silver Line Phase 2 design-build contractor is about to begin construction of the future Dulles Airport Station, one of six stations along Phase 2 of the Silver Line and located just south of Daily Garage 1 along Saarinen Circle.

The process will begin with mass excavation, a term used to describe the process of quickly removing large
amounts of material from a job site.

During a mass excavation process, large bulldozers, excavators, loaders and tandem dump trucks are used to dig out, load and take away dirt and rock at a rapid and efficient pace. At peak operation, as many as 15 dump trucks per hour may be moving into and out of the Dulles Airport Station job site.

Approximately 28,000 cubic yards of rock and 12,000 cubic yards of dirt will be removed from the Dulles Airport Station site during the excavation. Trucking routes will be carefully defined to minimize the impact on airport traffic.

The five Phase 2 at-grade stations will require an average of 13,000 cubic yards of mass excavation. Additional mass excavation operations will occur at some of the wayside facilities that support the rail system.

Some of the materials removed will be used as fill at other Phase 2 construction locations at Dulles International Airport.

Tower Crane Goes Up For Innovation Station

With temperatures near 90 degrees, Dulles Corridor Metrorail Project crews spent a July weekend assembling a tower crane in the median of the Dulles International Airport Access Highway, on the site of the Silver Line's future Innovation Center Station.

The crane tower (mast) rises approximately 187 feet and is outfitted with a 252-foot horizontal working arm (jib) able to lift 22,000 pounds of steel, concrete, large tools, generators and a wide variety of other building materials that will be used during the construction of the station. The crane's motors and counter weights are located in the shorter horizontal counter jib.

A second tower crane will be placed at the Herndon Station site in late 2015. Once the first crane has completed its work at Innovation Center Station it will be disassembled and moved onto the Reston Town Center Station site. Both cranes will be moved to the median of the Dulles Greenway to assist in the construction of the Loudoun Gateway and Ashburn Stations.


Photo Capital Rail Constructors

In Search of the Long-Eared Bat


Photo Northern Long-Eared Bat photo courtesy of Wetland Studies and Solutions, Inc.

Contractors building the rail yard, located on Dulles Airport property off Route 606 in Loudoun County, for Phase 2 are at the forefront of national efforts to save the Northern Long-Eared Bat, a recent addition to the U.S. Fish and Wildlife Service's (FWS) list of endangered species.

In mid-July the project undertook a week-long survey over seven nights from dusk to late night using nets to catch the bats which were identified for species and set free.

The creature is distinguished by its small size, large ears, and dark brown color and feasts on insects. These bats, whose population dropped 99 percent since 2006, are threatened by white-nose syndrome, a fungus that infects the environments where the bats hibernate.

The disease has killed more than 5.7 million bats in eastern North America, according to the FWS.

Construction sites in this region now must be surveyed to see if the Long-Eared Bats are roosting and raising their young before any work starts from mid-April through mid-September. "We are doing everything environmentally friendly that we can," said Stephen Barna, Package B project director.
The nightly vigils produced lots of bats but not a single Northern Long-Eared Bat which means construction work won't be delayed until mid-September.

But it's not so good for the little bats. "I think the fact that we have not found any Northern Long-Eared bats shows the extent of the demise," said John Nerich, lead construction specialist for the rail yard.


Bat captured on airport property
Photo Angela Cook

Silver Line Hailed at First Birthday Party


MWAA CEO Jack Potter and elected officials at Silver Line Anniversary

The Silver Line opened a year ago and business leaders, politicians and residents gathered in late July to celebrate as a long list of project proponents praised what many called the dramatic changes that continue to come to Tysons Corner and the entire Dulles Corridor because of the Silver Line.

Currently there are 20 plans for new mixed-use developments in Tysons. Experts said Tysons now <br> contributes more than $300 million to the Fairfax County tax base, a number that is expected to eventually hit $1 billion.

Wells + Associates reported on statistics that shows significant decreases in vehicular traffic in the Tysons area since the Silver Line opened:
  • 15 percent fewer cars at Scotts Crossing/Colshire Drive.
  • 11 percent fewer cars at Anderson Road/Dulles Access Highway off-ramp.
  • 7 percent fewer cars at Route 123 at Old Meadow Road/Capital One Drive.
Wiehle-Reston East Station, the temporary terminus of the Silver Line, continues to be the busiest station.

###

I think I may have mentioned this already, the tower crane setup at the site of the Innovation station is not the first time a tower crane was used to build a Metrorail station, George Hyman Construction used one to build the Arlington Cemetery station.

Link to PDF version at Dulles Corridor Metrorail Project web site.

John in the sand box of Maryland's eastern shore.
__________________
John in the sand box of Maryland's eastern shore.
Reply With Quote
     
     
  #1103  
Old Posted Aug 7, 2015, 8:51 PM
202_Cyclist's Avatar
202_Cyclist 202_Cyclist is offline
Registered User
 
Join Date: Feb 2009
Posts: 5,952
Capital Bikeshare to get new bicycles, add nearly 60 stations starting this fall

Capital Bikeshare to get new bicycles, add nearly 60 stations starting this fall

By Luz Lazo
August 3, 2015
Washington Post

"After a nearly two-year delay, Capital Bikeshare will get new bicycles and docking stations at almost 60 new locations throughout the region starting this fall.

The additional bikes and docking stations will allow the popular bike network to continue what had been rapid growth in the Washington area since it began operating in 2010. There are already more than 3,000 bikes and 354 stations in the District, Alexandria, and Arlington and Montgomery counties.

Capital Bikeshare had to call a halt to its plans to expand after its main bicycle manufacturer, the Montreal-based Public Bike System Co., went bankrupt in early 2014, hindering the purchase of more of the distinctive red bikes. The delay could not have come at a worse time for Capital Bikeshare. It has more than 29,000 members, surpassing 10.5 million trips, and demand is growing..."

http://www.washingtonpost.com/local/...0ee_story.html
Reply With Quote
     
     
  #1104  
Old Posted Aug 25, 2015, 3:23 AM
cambron J's Avatar
cambron J cambron J is offline
Registered User
 
Join Date: Jul 2012
Posts: 150
Dulles Corridor Metrorail Project Pictures 08 23 2015

Work has commenced on the excavation of the tunnels that will hold the conduits that will carry third rail power from the substation to the right of way east of Dulles Airport. Work continues on the installation of the 34.5 KV power feed bus.

Grading work continues from roughly Centreville Road to the location of the east abutment north of Autopilot Drive.

The foundations for the Innovation Center station are mostly done. A tower crane has been erected at what looks like mid platform in the track bed of track N2, north side, of the station.

The east abutment north of Autopilot Drive is well underway.

Excavation for the Dulles Airport station mezzanine has begun. The lanes of Saarinen Circle have been shifted to accommodate the excavation.

There were reports of cracks in the precast girders shortly after they were set on the columns along Air Fright Lane in April. No reports have been made as what will be done with those girders. It seem the cracking issues has been addressed as the Track N2 girders were set on the columns north of the Hertz Rent-a-car entrance on Autopilot Drive.

All but a couple of the mainline columns from southern most column along Airfright Lane to the shoulder of the Dulles Greenway are done. Most of the columns for the east yard lead are done and all of the west yard lead column are done from the junction of the yard leads to the shoulder of the Dulles Greenway. The column for the straddle bents that will support both the mainline and the west yard lead have been built. Work on the column piles in the median of Dulles Greenway has not begun yet.

<b>Test track and Commissioning Facility</b>

The commissioning facility building has been turned over to WMATA and is now being used by the folks charge with making the 7k cars revenue ready.

The multilevel parking structure has also been turned over to WMATA and is being used by employees.

The test track ballast has been groomed to its finished elevation. Third rail section have been installed but have not been bolted and bonded. The track circuits Wee-Z bonds and marker coils to control automatic station stops have been installed.

###

Pictures at picasaweb.google.com/cambronj DCMP 08 23 1015.
Pictures at picasaweb.google.com/cambronj Greenbelt Test Track and Commissioning Facility.
Captioned thumb nails along with the above and past essays can be view at cambronj.blogspot.com DCMP 08 23 2015.
__________________
John in the sand box of Maryland's eastern shore.

Last edited by cambron J; Aug 26, 2015 at 2:01 AM.
Reply With Quote
     
     
  #1105  
Old Posted Sep 27, 2015, 8:09 PM
cambron J's Avatar
cambron J cambron J is offline
Registered User
 
Join Date: Jul 2012
Posts: 150
Dulles Corridor Metrorail Project progress update e-mail 09 22 2015

Silver Line Phase 2 Rail Yard and Maintenance Facility


Q: Where is the rail yard located?
A: The rail yard and maintenance facility will be located on Dulles Airport Property along Route 606.

Q: How large is the facility?
A: The facilities and tracks will be built on approximately 90 acres.

Q: What is its function?
A: The rail yard will be used to store trains overnight and as needed. The rail yard will have a capacity of 168 rail cars. The maintenance facility will consist of five service buildings that will be used to maintain and repair trains.

Q: How will the public be affected by this portion of the Dulles Corridor Metrorail Project?
A: Construction of the rail yard and maintenance facility will have a small impact on the public as the majority of the work will take place on Dulles Airport property. However, traffic on Route 606, a major commuter artery, will be minimally impacted by project trucks and employee vehicles traveling through Mercure Business Park.

Q: How much does it cost?
A: $250 million.

Q: Who is the contractor?
A: The primary contractor for the rail yard and maintenance facility is Hensel Phelps, a Chantilly-based company.

Q: When does construction begin? When is it expected to end?[/b]
A: Construction began in July 2015 and is expected to complete in Fall 2018.

Q: What construction will be taking place in Fall 2015?
A: As of September, the contractor is working to complete the initial phases of construction including relocating staff and preparing the land for the facility. Current work taking place includes:setting up trailers, installing E&S measures, clearing & grubbing and rough grading the site.
During next few months, the grading operation will continue, in addition to the installation of storm sewers and drainage structures. A blasting operation to crush the bedrock is being plannedin
coordination with Dulles Airport, Fairfax and Loudoun Fire Departments.

Q: How can I learn more:
A: For general project inquires email <a href="mailto:outreach@dullesmetro.com">outreach@dullesmetro.com</a> or visit <a href="http://www.dullesmetro.com/" target="_blank">www.dullesmetro.com</a>.[b]

Stephen Barna Leads Rail Yard & Maintenance Facility Construction


Photo courtesy of Dulles Corridor Metrorail Project

Stephen Barna serves as the project director for the $260M Rail Yard and Maintenance Facility Contract, also known as Package B. Package B consists of the construction of the new Metro Silver Line Rail Yard and Maintenance Facility located on the north side of Dulles Airport property.

Barna has a history with Metrorail construction. He began his career with a local general contractor on the original Blue Line construction. His experience as superintendent for the King Street Station and rail line in Alexandria, among other Metrorail projects, served him well overseeing the Phase 1 construction of the Tysons Corner tunnel and aerial guideways.

"Design and construction of the Silver Line Project is an incredible challenge. Along with the rail line we are building bridges, stations and the entire infrastructure it takes to operate the system.

That includes electrical power, communications, water, sewer, highway improvements, etc."
With decades of experience, Barna came to the project in 2009. His current work on the Rail Yard and Maintenance Facility has proven to have different challenges than his experience in Phase 1 constructing the Silver Line in the densely developed urban area of Tysons Corner.

"The Rail Yard and Maintenance Facility site is a 90-acre completely undeveloped area. It has its own set of unique environmental and construction challenges to be overcome. The new few years will be exciting as construction moves forward and the facility begins to take shape."

Barna received a bachelor's degree in civil engineering from Virginia Polytechnic Institute and State University and is a Registered Professional Engineer in Virginia, Maryland and the District of Columbia.

Soil Relocation along Route 606 Completed

During Phase 1, the rail project stockpiled dirt removed from Tysons Corner on 40-acres that are now part of rail yard site. The 1.3 million cubic yards was relocated and the site re-graded to accommodate the new construction. Atlantic Contracting and Materials Company served as the contractor for the soil removal project.


Photo courtesy of Dulles Corridor Metrorail Project

Rail Yard and Maintenance Facility Location


*Yellow Area = Rail Yard and Maintenance facility

###

Link to PDF version at Dulles Corridor Metrorail Project web site.
__________________
John in the sand box of Maryland's eastern shore.
Reply With Quote
     
     
  #1106  
Old Posted Oct 29, 2015, 11:59 AM
cambron J's Avatar
cambron J cambron J is offline
Registered User
 
Join Date: Jul 2012
Posts: 150
Dulles Corridor Metrorail Project Pictures 10 25 2015

Excavation for the foundations at the Herndon station has begun.

Most of the sound wall at the Innovation Center Station are complete. The foundation for tower crane is within the footprint of the north, track N2 sound wall, not in the N2 track way as noted in my previous post.

The bridge girders over Centerville Road have been set. They are of the same design as the girders over Horsepen Run.

The right of way barrier walls east of Rudder Road have proceeded several hundred feet more further east.

Columns have begun to come out of the ground west of the east abutment west of Rudder Road.

Excavation at the airport station on the mezzanine side of the of the pedestrian tunnel is nearly complete. Columns have begun to come out of the ground west of the station.

All of the mainline columns from the southern most column along Airfright Lane to the shoulder of the Dulles Greenway are done. Girders continue to be set heading north along Autopilot Drive, as of this date 36 have set along Autopilot Drive and 8 along Airfright Lane.

All of the column in the Dulles Yard lead Y are done. I did not go back into the woods to check the progress on rest of the the columns west of the east lead junction, I think we are safe to assume they are mostly done.

No work has begun on the columns in the median of the Dulles Greenway.

Land is being cleared on the north side of the Dulles Greenway to make way for the entrance at the Loudoun Gateway station. Land is also being cleared on the south side for what appears to be a staging area.

Land is being cleared on the remainder of the site at Dulles Yard.

Most of the girders between the abutments over Broad Run have been set. To reduce the disruption to traffic on the Dulles Greenway the contractor built the column in the stream bed and set those girders before building the abutments and setting the on girders either side of the stream.

Test track and Commissioning Facility

The track work on the test track is done. The signals at the crossover are in place south of the E10 Greenbelt interlocking and are covered with bags. The marker coils for the simulated station alone with the signage marking the location of the ends of the station are in place. The simulated station is located under the Greenbelt Road overpass. The north end is roughly 185' north of the north side of the overpass. The center of the platform is located at roughly E 609+95.

###

Pictures at picasaweb.google.com/cambronj DCMP 10 25 2015.
Companion dash cam video Wiehle Reston - East To Saarinen Circle 10 25 2015 .
Pictures at picasaweb.google.com/cambronj Greenbelt Test Track and Commissioning Facility.
Captioned thumb nails along with the above and past essays can be view at cambronj.blogspot.com DCMP 10 25 2015.
__________________
John in the sand box of Maryland's eastern shore.
Reply With Quote
     
     
  #1107  
Old Posted Nov 18, 2015, 4:36 PM
202_Cyclist's Avatar
202_Cyclist 202_Cyclist is offline
Registered User
 
Join Date: Feb 2009
Posts: 5,952
Md. receives four proposals to build light-rail Purple Line

Md. receives four proposals to build light-rail Purple Line

By Katherine Shaver
November 17, 2015
Washington Post

"Maryland just moved another step closer to building a light-rail Purple Line in the Washington suburbs.

As of noon Tuesday — the deadline for submitting “technical” bids — the Maryland Transit Administration (MTA) had received proposals from four teams of private companies outlining how they would design, build, operate and maintain a Purple Line, state officials said.

All cost details — the overall construction cost and how much the state would pay the private team to operate and maintain the line, as well as help finance its construction — will be included in financial proposals due Dec. 8..."

https://www.washingtonpost.com/news/...l-purple-line/
Reply With Quote
     
     
  #1108  
Old Posted Nov 26, 2015, 4:35 AM
cambron J's Avatar
cambron J cambron J is offline
Registered User
 
Join Date: Jul 2012
Posts: 150
WMATA: Dulles Corridor Metrorail Project progress update e-mail 11 24 2015

Putting Finishing Touches on Phase 1


Art was installed in late November at the McLean Station.
Photo courtesy of Dulles Corridor Metrorail Project.

While Phase 1 of the Silver Line continues normal operations through Tysons to Wiehle Avenue in Reston, Dulles Corridor Metrorail Project crews are finalizing the details of the stations and adjacent areas.

Stations

To enhance illumination and improve fixtures in the stations, new LED lights are being installed in handrails and are expected to be complete by the end of 2015. These lights have been tested at the Greensboro Station with successful results. Additional light studies will be done at each station to see if any additional
improvements are needed.

Route 7

Drivers will see work taking place along Route 7 and other parts of Tysons Corner. Work will consist primarily of concrete repair and enhancement to implement new Americans with Disabilities Act guidelines.

Art in Transit

Artwork at the Phase 1 stations is expected to be complete in Spring 2016. While the McLean and Wiehle-Reston East Stations will be getting stained glass in the station mezzanine, the Greensboro and Spring Hill Stations will be home to lighted sculptures. Art installation at the Tysons Corner Station is complete.

Pardon our Dust Along the Phase 2 Alignment

Rail project crews are making some major changes to road patterns to accommodate project construction along the project alignment.

Recently work began on the sewer and water lines at the Herndon-Monroe Park & Ride. These lines will serve the parking facility and future Herndon Metro Station being constructed in the median of the Dulles Access Road.

Commuters will be impacted by the relocation of the Kiss & Ride, some bus bays and slug lines. Signage detailing these changes is currently displayed at the Herndon-Monroe Park & Ride to aid drivers and transit users. Fairfax Connector and WMATA bus riders are encouraged to stay alert to notifications that communicate future changes.

Starting mid-November, the ramp from eastbound Aviation Drive to the eastbound Dulles International Airport Access Highway will close for approximately one year because of construction of the aerial guideway. Signs will direct drivers to a new ramp that will provide access to the Access Highway.

What's Happening at Phase 2 Stations


Construction of the Dulles Airport Station.
Photo Courtesy of Capital Rail Constructors.

Reston Town Center Station:

The installation of support of excavation and bearing piles will begin in December and continue into the winter months.

Herndon Station:

Excavation of the site has begun, and 6,000 cubic yards of dirt of have been removed to make room for the station. A tower crane will be erected in early December for the construction of the station foundation.

Innovation Center Station:

To date, 1,902 cubic yards of concrete have been placed for the footings and track wall. Crews will be erecting 170 structural and architectural precast concrete elements and continue the installation through the winter. Structural steel erection is scheduled to begin in February.

Dulles Airport Station:

Excavation of the station is nearly complete, with more than 35,000 cubic yards of soil and rock removed to date. By late November, excavation of the Elevator Machine Room, which is the deepest part of the station at nearly 40 feet below Saarinen Circle, will be complete. Cast-in-place concrete operations will then begin and continue for approximately nine months.

The 34.5kV duct bank that will bring power to both the station and the trains is scheduled to be completed in December. Forming of the concrete columns to support the station began in November.

The pedestrian tunnel between Daily Garage 1 and the airport will close in early January while utilities are relocated and the moving walkways are modified to accommodate tunnel's tie-in to the future station. During the closure period, shuttle bus frequency will increase to transport travelers from the garage to the main terminal. The duration of this closure is not yet known.


Pier Construction of the Aerial Guideway continues at Dulles Airport.
Photo by Jennifer Alcott of Capital Rail Constructors.

###

Link to PDF version at Dulles Corridor Metrorail Project web site.
__________________
John in the sand box of Maryland's eastern shore.
Reply With Quote
     
     
  #1109  
Old Posted Dec 8, 2015, 9:31 PM
202_Cyclist's Avatar
202_Cyclist 202_Cyclist is offline
Registered User
 
Join Date: Feb 2009
Posts: 5,952
Plans for higher-speed rail between Richmond and Washington on track

Plans for higher-speed rail between Richmond and Washington on track

By Luz Lazo
December 8, 2015
Washington Post


Image courtesy of the Washington Post.

"Virginia is moving forward with a plan to speed train travel between Washington and Richmond by 2025.

The state’s rail agency and the Federal Railroad Administration are exploring the feasibility of higher-speed rail on the 123-mile stretch connecting the two capital cities. Midway through a federal environmental review, the agencies have identified possible improvements, including adding a third track all along the corridor, adding passing sidings and crossovers to allow trains to pass one another more easily, and straightening some curves to achieve faster speed.

Over the past few months engineers have also identified locations where the track could be straightened to allow for higher speeds. The plan, officials say, is to raise the maximum rail speed from the current 70 mph to 90 mph, and in doing so, make intercity passenger rail more reliable for people in the corridor and more competitive with car and air travel..."

https://www.washingtonpost.com/news/...gton-on-track/
Reply With Quote
     
     
  #1110  
Old Posted Dec 16, 2015, 7:58 PM
202_Cyclist's Avatar
202_Cyclist 202_Cyclist is offline
Registered User
 
Join Date: Feb 2009
Posts: 5,952
District says streetcars starting final dry run but still need safety sign-off

It's incredibly donkey-brained not to operate the streetcar on Sunday. I remain a supporter of the streetcar but it seems that Sunday would be one of the busiest days for a corridor with a lot of restaurants and retail. Perhaps mid-day on a Tuesday would be better for system maintenance.

District says streetcars starting final dry run but still need safety sign-off


"A streetcar sits on the rails along H Street NE near the intersection with 4th Street in Washington." (Eva Russo/For The Washington Post)

By Michael Laris
December 15, 2015

"Officials pushing to open the District’s streetcar line to passengers early next year said they will launch a formal dry run, known as “pre-revenue operations,” starting Wednesday.

But even before carrying its first passenger, the District has spent more than $13 million on the operation and maintenance of the system, according to city figures....

A spokesman for the District Department of Transportation said Tuesday that when the doors open to the public, streetcars will run six days a week, with no passenger service after 2 a.m. on Sundays. The city had already rolled back the frequency of daily service, which officials say will run every 15 minutes instead of every 10 minutes...."

https://www.washingtonpost.com/local...433_story.html
Reply With Quote
     
     
  #1111  
Old Posted Dec 23, 2015, 2:44 PM
202_Cyclist's Avatar
202_Cyclist 202_Cyclist is offline
Registered User
 
Join Date: Feb 2009
Posts: 5,952
Metro adds the proposed Potomac Yard station to its rail system

Metro adds the proposed Potomac Yard station to its rail system

By Luz Lazo
Washington Post
Dec. 22, 2015

"The planned Metro station in Alexandria’s growing Potomac Yard community is officially part of the region’s passenger rail system.

At the final meeting of 2015 last week, the Metro board of directors voted to incorporate the proposed station into its 91-station system, taking an important step to move the project forward.

The Metro board backed the city’s choice for a $268 million rail stop between the CSX railroad tracks and George Washington Memorial Parkway and gave authority to General Manager Paul J. Wiedefeld to negotiate property for the project..."

https://www.washingtonpost.com/news/...s-rail-system/
Reply With Quote
     
     
  #1112  
Old Posted Jan 7, 2016, 6:14 PM
202_Cyclist's Avatar
202_Cyclist 202_Cyclist is offline
Registered User
 
Join Date: Feb 2009
Posts: 5,952
Residents along path of proposed Purple Line told to move fences, sheds

Residents along path of proposed Purple Line told to move fences, sheds


Ajay Bhatt outside his new fence. (Michael S. Williamson/The Washington Post)

By Katherine Shaver
January 6, 2015
Washington Post

"Some Maryland residents along the planned route for the light-rail Purple Line are being told that they have until April 30 to tear down fences, sheds and anything else built on publicly owned land preserved for the project.

About 80 property owners in the Washington suburbs of Bethesda and Chevy Chase have begun receiving letters from the Montgomery County Department of Transportation ordering them to remove structures that “encroach” on a county-owned trail behind their homes.

The county plans to rebuild the three-mile jogging and cycling trail between downtown Bethesda and Silver Spring alongside train tracks as part of the state’s 16-mile light-rail project..."

https://www.washingtonpost.com/local...79a_story.html
Reply With Quote
     
     
  #1113  
Old Posted Jan 7, 2016, 7:17 PM
Busy Bee's Avatar
Busy Bee Busy Bee is online now
Show me the blueprints
 
Join Date: Feb 2006
Location: on the artistic spectrum
Posts: 10,404
"Mister Ajay Bhatt — tear down this fence!"
__________________
Everything new is old again

There is no goodness in him, and his power to convince people otherwise is beyond understanding
Reply With Quote
     
     
  #1114  
Old Posted Jan 18, 2016, 8:47 PM
cambron J's Avatar
cambron J cambron J is offline
Registered User
 
Join Date: Jul 2012
Posts: 150
Dulles Corridor Metrorail Project Pictures 01 17 2016

Utility tunneling under the Access / Toll Roads at the Reston Town Center and Herndon stations continues. Tunneling under the Access / Toll Roads for the third rail conduits is also underway along with continuing work on the 34.5 KV power feed bus.

Foundations for the right of way barrier walls are being installed between Herndon and Innovation Center, rebar for the barrier walls are visible on some of the foundations. Barrier wall installation continues to move east from Rudder Road to Horsepen Run.

Some preliminary ground work is taking place at Reston Town Center station.

Excavation at the Herndon station continues, a tower crane has also been erected on the track N2 side of the station.

The barrier walls along the entire length of the Innovation Center station are done. Columns that will support the mezzanine and mezzanine canopy are up to the level of the mezzanine.

The south straddle bent that will carry the elevated over the eastbound Access Road north of Aviation Drive was recently poured as it still has its protective blanket covering it. All of the columns west of the east elevated abutment in the median of the Access Road are near completion. The foundations for the straddle bent columns that will carry the elevated over the eastbound Access Road south of Aviation Drive have are done. One of the columns for the straddle bents that will carry the elevated over the eastbound Access Road south Aviation Drive has come out of the ground. No other column foundations work east of the airport station is underway.

Excavation of the airport station mezzanine is complete. The invert has been poured and preparation for the floor slab has begun. The Garage 1 pedestrian tunnel was closed on 01 11 2016 to allow the modification to the tunnel to allow the connection of the station entrance. See Section at Center Line Pedestrian Tunnel N10-NGA-A-303 in the airport station post for the detail of the modification.

All of the columns west of the airport station south of Aviation Drive are various stages of completion.

The remainder of girders have been set on the columns along Autopilot Drive to the 2nd column north of Materials Road. Pouring of the concrete deck has follow the setting of the girders. The contractor moved the cranes 9 columns north of Materials Road and began moving south, they have set 3 of those spans.

The yard lead columns appear to be mostly complete. Jersey barriers have been placed along the right shoulder of the westbound Dulles Greenway in preparation for the lane shift to allow the construction of the mainline elevated flyover, west yard lead elevated flyover, abutments and yard lead junction. No work in the Median of the Dulles Greenway has begun in this area.

Clearing and leveling that involves the use of explosives is taking place on the south side of the Dulles Greenway at the Loudoun Gateway station. (in my previous post I noted this as a staging area) Material from that clearing is being moved to entrance area north of the Dulles Greenway. No work in the median at the site of the Loudoun Gateway station has begun.

The east and west abutments at Broad Run have not been constructed.

A column in the median of Dulles Greenway that will carry Central Station Drive at the Ashburn station has been built. No work in the median at the site of the Ashburn station has begun.

Clearing of the site of the Dulles Yard is well underway. The contractor has graded what appears to be loop tracks at the south end of the site.

###

Pictures at picasaweb.google.com/cambronj DCMP 01 17 2016.
This and previous posts in this series can be seen at cambronj.blogspot.com.
Companion dash cam video shot westbound along Dulles Access Road from Wiehle Avenue in Reston to Saarinen Circle in front of Garage One
__________________
John in the sand box of Maryland's eastern shore.

Last edited by cambron J; Jan 19, 2016 at 12:51 AM.
Reply With Quote
     
     
  #1115  
Old Posted Jan 29, 2016, 9:32 PM
202_Cyclist's Avatar
202_Cyclist 202_Cyclist is offline
Registered User
 
Join Date: Feb 2009
Posts: 5,952
Georgetown-Rosslyn gondola study takes flight (Washington Post)

Georgetown-Rosslyn gondola study takes flight


By Patricia Sullivan
January 28, 2016
Washington Post

"The Arlington County Board agreed Thursday night to kick in $35,000 to study the possibility of a Georgetown-to-Rosslyn gondola, which supporters hope will ease traffic on Key Bridge and zip visitors more easily across the Potomac River.

“I started out really skeptical, and I’m still skeptical, but I want to have an open mind,” said board chair Libby Garvey (D), just before the unanimous vote supporting the study. “This doesn’t mean it’s a done deal by any means, but we’ll take a look at it.”

Joe Sternlieb, president of the Georgetown Business Improvement District, told the board that an urban gondola, or “cable-propelled transit,” could be faster and far cheaper than building a new Metro tunnel to Georgetown, which lacks a subway stop..."

https://www.washingtonpost.com/local...5ce_story.html
Reply With Quote
     
     
  #1116  
Old Posted Jan 29, 2016, 9:56 PM
Busy Bee's Avatar
Busy Bee Busy Bee is online now
Show me the blueprints
 
Join Date: Feb 2006
Location: on the artistic spectrum
Posts: 10,404
Quote:
Originally Posted by 202_Cyclist View Post
Residents along path of proposed Purple Line told to move fences, sheds


Ajay Bhatt outside his new fence. (Michael S. Williamson/The Washington Post)
In case you hadn't heard, this guy got his bhatt handed to him by the Maryland court of appeals, preventing residents ability to claim "ownership" of the past and future railroad ROW, thus paving the way for Purple Line construction:

Read about it here.
__________________
Everything new is old again

There is no goodness in him, and his power to convince people otherwise is beyond understanding
Reply With Quote
     
     
  #1117  
Old Posted Feb 18, 2016, 7:36 PM
202_Cyclist's Avatar
202_Cyclist 202_Cyclist is offline
Registered User
 
Join Date: Feb 2009
Posts: 5,952
Dc streetcar starting service next saturday!!!

Woo-hoo!

BREAKING: H Street streetcar will carry passengers on February 27, says Bowser
http://greatergreaterwashington.org/...7-says-bowser/

The DC Streetcar Will Start Service in a Week
http://dc.urbanturf.com/articles/blo...n_a_week/10891


Image courtesy of the DC Department of Transportation.
Reply With Quote
     
     
  #1118  
Old Posted Feb 19, 2016, 2:55 AM
dabcom dabcom is offline
Registered User
 
Join Date: Mar 2003
Posts: 694
Quote:
Originally Posted by 202_Cyclist View Post
Woo-hoo!

BREAKING: H Street streetcar will carry passengers on February 27, says Bowser
http://greatergreaterwashington.org/...7-says-bowser/

The DC Streetcar Will Start Service in a Week
http://dc.urbanturf.com/articles/blo...n_a_week/10891


Image courtesy of the DC Department of Transportation.
Awesome!
Reply With Quote
     
     
  #1119  
Old Posted Feb 19, 2016, 3:12 AM
dc_denizen's Avatar
dc_denizen dc_denizen is offline
Selfie-stick vendor
 
Join Date: Oct 2005
Location: New York Suburbs
Posts: 10,999
the streetcar has taken what, only 15 years.
__________________
Joined the bus on the 33rd seat
By the doo-doo room with the reek replete
Reply With Quote
     
     
  #1120  
Old Posted Feb 19, 2016, 6:38 AM
Eightball's Avatar
Eightball Eightball is offline
life is good
 
Join Date: Jun 2013
Location: all over
Posts: 2,301
H Street streetcar!! Whoa! Plus they pushed out the DCFEMS SSO boozo so future extensions should open in a timely manner...
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Discussion Forums > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 10:17 PM.

     
SkyscraperPage.com - Archive - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2024, vBulletin Solutions, Inc.