Update - November 2015:
Quote:
We acknowledge that Tower Melbourne has been
delayed close to 2 years now due to the legal dispute
with the adjoining owner who has raised objections in
regards to the proposed protection works that form
part of the demolition procedures involved to
demolish the existing building on the project site.
We fully understand, and share your frustration with
this delay. No one wants to see Tower Melbourne
completed more than we do. To that end, we remain
fully committed to seeing this vision realised.
This has been a long and drawn-out situation, it has
been frustrating for us all, but we know that the end
result will be worth the wait.
While the dispute concerning protection works is
currently ongoing, we are now confident that we have
made considerable progress through the process that
has been forced upon us.
Previously we advised of the removal of a number of
legal actions taken by the adjoining owner. The
remaining matters are now more streamlined and have
been progressed. Consequently, we do expect to obtain
some positive results within the next month or so.
There will be further matters that will need to be
completed before works can re-commence, and
unfortunately we do not have a date that we are able to
advise when that will occur.
At this time we can only advise we are progressing.
The end of the delay is getting closer. Works will
recommence, it is purely a matter of time and process
to enable this to occur.
Once more, we reiterate our continued commitment to
Tower Melbourne, and again thank you for your
continued patience and understanding in this matter.
|