Posted Nov 4, 2016, 4:19 PM
|
Registered User
|
|
Join Date: Nov 2012
Location: Winnipeg
Posts: 13,785
|
|
Quote:
Originally Posted by alittle1
If anyone is wondering why I haven't sent a finalization to this project, it is because it has not been completed as of today. They are still playing around and patching up the mistakes that were made during construction. Therefore, March, 2017.....still does not seem out of line.
PCL did move their trailers (offices) out in September, I would imagine that they secured another job(site) where they could get FREE rent and just hookup the phones.
|
PCL moved all the crap out to south Winnipeg for the transitway project.
|