someone can explain me please why the cubic base has not been completed since at least 8 months ???

i thought thet would cover it with glass panels...

but, one year later, it is the same !!

in spite of this, the glass on the main part of the tower is added every week ...
The original design had a problem during fabrication and the glass kept shattering due to the V notch in the back that formed the prism. So a new design / build contract was initiated and awarded this year. The renderings of what it looks like have been posted in the forum and Permetilistia has been busing installing the clips to support the "podium glass". You should expect to see the glass start being installed late this year.