View Single Post
  #255  
Old Posted Jan 6, 2022, 4:02 AM
chris08876's Avatar
chris08876 chris08876 is offline
NYC/NJ/Miami-Dade
 
Join Date: Jul 2013
Location: Riverview Estates Fairway (PA)
Posts: 45,840
NEWARK BAY-HUDSON COUNTY EXTENSION WIDENING AND RECONSTRUCTION

Quote:
Location: Hudson and Essex Counties

Description: The Newark Bay-Hudson County Extension will be reconstructed and widened from two lanes in each direction to three or four between the mainline of the Turnpike at Interchange 14 and the Columbus Drive Exit. Nearly 80 percent of the 8.1-mile Extension is carried on bridge structures. Those structures are nearing the end of their design service lives and now require regular, significant, and costly maintenance. What’s more, traffic growth and substantial port-related heavy truck activity have degraded operating conditions in the corridor. Significant congestion and delays are a daily occurrence and have contributed to the poor condition of the roadway pavement and bridges. This widening and reconstruction program will include the replacement of several bridges, including the Newark Bay Bridge.

Schedule: Environmental studies and preliminary engineering began in 2021. Final design is expected to begin in 2023. Construction is expected to begin in 2026. The duration of the full program is expected to be 10 to 15 years.




===============
https://www.njta.com/capitalprojects
Reply With Quote