Originally Posted by mrnyc View Post
so all that hand wringing and hoo ha and no l-pocalypse.

basically, hanging the wires and bondo-ing up the tunnel bench wall is fine.



Speedy cable installation latest step forward in fast-moving L-train East River tunnel repair job Brooklynites once dreaded

Clayton Guse
By CLAYTON GUSE
NEW YORK DAILY NEWS |
JUL 28, 2019


It took a contractor just two weekends to finish a big chunk of the L-train East River tunnel repair project, which the MTA says is moving along swiftly.

Workers hung 40,000 feet of cable along a wall of the Canarsie Tunnel’s northern tube during the two weekends over the last month. Construction crews will install cable racks on the other half of the tunnel in the coming months.


more:
https://www.nydailynews.com/new-york...piq-story.html
The tunnel will still need a complete rebuild this just kicks it down the road...which is problem in this region.