Does anybody have information on the timetable for wrapping up the caison work and beginning the actual excavation? Since they've been at the caisons for around 15 months now (first post showing that here was in Jan 2017), you'd think they'd be close to finishing that.
Pile installation started in July 2017 and should be wrapping up within the next month or so (from what I've observed).

During Jan and Feb of 2017, the piling work was just for the test piles. Since the drill rig is so large it just sat on the site after it had completed those piles making it seem it was working.

I'd assume excavation will be underway by May or June 2018, but I don't know specifics for that.

Before they can start excavation they also need to finish the shoring wall which is more than halfway complete, the first part being installed in May/June 2017 and the other sections being installed from Nov 2017 to Jan 2018, maybe they will finish the wall in April or May 2018 would be my guess.

You can follow this page for updates;
http://www.swinertonwebcor.com/updates/

Also, Mission Street tower has a tower crane permit