Another recent article provides more detail about the construction process and schedule. The crane can be expected to remain up for at least the next year. Final completion is scheduled for April-June 2019. The article title is a bit of a 'no-duh' - still an interesting read though for those not too familiar with the project.

Quote:
15-story Exchange Building project will proceed floor by floor
By Al Jones | MLive
October 23, 2017

...About two years of work -- in total -- will be necessary to make the mixed-use commercial and residential project a reality, said Gregory A. Taylor, principal of Phoenix Properties LLC. "We're scheduled to complete the project in April to June of 2019," said Taylor, who provided an update on the project to members of the Kalamazoo Rotary Club at noon Monday in downtown Kalamazoo...