Quote:
Originally Posted by winlinmac001 View Post
So, when are they installing the last and final segment of the spire? It's been sitting at the base of the tower for the last few days.

Are the construction workers installing the electrical and other utility wires at the same time as they place each segment of the spire, or will they do that after completing the spire installation?
They have to put in the communication rings first that would not be able to be installed by tower boom being obstructed by remaining upper spire sections. meanwhile 5 star electric is busy working up the top two sections with revolving beacon and aviation beacons which is a few weeks worth of work. Then we need a few days straight of low winds to jump the tower crane, set the top sections and jump back down.