Keiwit will start construction on the final 9.5 miles of the I-225 LRT line, very soon. Construction is scheduled to be fully complete by mid-2015 (only 2.5 years away) and then followed by 6 months of testing before it goes operational in early 2016.

That brings this total:
Denver West & 225 lines - 14 miles
Up to 22.6 miles for LRT under construction in Denver