In recent weeks they have been working on putting in the extra lanes following the underpass. I was hoping there would be more progress on the actual construction of the underpass. The city of Winnipeg has the following timeline currently up:
◾Two lanes of the Project on Plessis Road between Dugald Road and Kernaghan Avenue will be open to traffic by October 31, 2015, as opposed to July 31, 2015;
◾Four lanes of the Project on Plessis Road between Dugald Road and Kernaghan Avenue will be open to traffic by September 30, 2016, as opposed to September 30, 2015; and
◾The Project completion date will be no later than March 31, 2017, as opposed to March 31, 2016.
When it first started two lanes were supposed to be open to traffic Dec 2014.
|