Construction Schedules/Milestones
April 2005 Construction begins
Fall 2006 Structures from Gateway Boulevard to 66th Street completed
Fall 2006 Mainline paving from Gateway Boulevard to 34th Street completed
Fall 2007 Structures from 50th Street to Highway14/216 Interchange completed
October 2007 Balance of mainline paving and Interchange paving completed
October 2007 Anthony Henday Drive S.E. opens
October 2007 Operations and maintenance begins